Update on cycle schemes

1. Dodder Greenway

Environmental and screening currently ongoing. Progressing to Part 8 approval by end of 2016. Funding of €188,000 committed until end of 2016.

2. Tallaght to Ballyboden

Works recently completed at Knock Lyon Junction. Funding of €465,000 committed until end of 2016.

3. Grange Road

Construction works commenced on site at Sarah Curran Avenue to Park Avenue. Funding of €315,000 committed until end of 2016.

4. Ballyroan Green Schools

Construction to commence on site in the next 4 weeks. Funding of €469,000 committed until end of 2016.

5. Tallaght to Templeogue Green Route

Nearing completion, Landscaping underway and Parking control being implemented in the Village.

6. Willsbrook Road Cycle facilities

Construction underway, completion due in January 2017.

7. Monastery Road walking route

Phase 3 to the Village completed. Approval from the NTA to design section from Monastery Heath to the Luas. 

8. Tallaght to Liffey Valley

Progressing to detailed design of the Scheme and approval will be sought for funding next year.

9. N4 to City Centre Scheme - Woodies Junction

Detailed negotiations with the NTA are underway.

10. Walkinstown Roundabout

Awaiting results of the QBC study which will allow progress, we expect these results within the next two months.