COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, September 26, 2016
QUESTION NO.11
QUESTION: Councillor D. Looney
To ask the Chief Executive for an update on all cycle schemes relevant to the County following recent media announcements regarding funding for such, and to make a statement on the matter.
REPLY:
Update on cycle schemes
1. Dodder Greenway
Environmental and screening currently ongoing. Progressing to Part 8 approval by end of 2016. Funding of €188,000 committed until end of 2016.
2. Tallaght to Ballyboden
Works recently completed at Knock Lyon Junction. Funding of €465,000 committed until end of 2016.
3. Grange Road
Construction works commenced on site at Sarah Curran Avenue to Park Avenue. Funding of €315,000 committed until end of 2016.
4. Ballyroan Green Schools
Construction to commence on site in the next 4 weeks. Funding of €469,000 committed until end of 2016.
5. Tallaght to Templeogue Green Route
Nearing completion, Landscaping underway and Parking control being implemented in the Village.
6. Willsbrook Road Cycle facilities
Construction underway, completion due in January 2017.
7. Monastery Road walking route
Phase 3 to the Village completed. Approval from the NTA to design section from Monastery Heath to the Luas.
8. Tallaght to Liffey Valley
Progressing to detailed design of the Scheme and approval will be sought for funding next year.
9. N4 to City Centre Scheme - Woodies Junction
Detailed negotiations with the NTA are underway.
10. Walkinstown Roundabout
Awaiting results of the QBC study which will allow progress, we expect these results within the next two months.