"To ask the Chief Executive can an update be given on where the CPO process is at for Gaelscoil Cnoc Liamhna? What timecales are involved?"

REPLY:

The CPO for Gaelscoil Chnoc Liamhna Knockylon was published on 24th March 2016 and the public display period will run up to and including 6th May 2016. Once the public display period has ended South Dublin County Council will have an indication as to the exact timescale involved complete the CPO.

As requested, the general timescale for the Compulsory Purchase order process are outlined below:-

Local Authority makes CPO (week 1) – 24th March 2016.

Public Display period 6 weeks (week 1-6) - up until 6th May 2016.

An Bord Pleanala 18 week objection period to determine the matter (weeks 7-19)

Estimated date of oral hearing if necessary – approx. 14 weeks after CPO made by Local Authority if there are any objections and or modified (week 14)

CPO confirmed by An Bord Pleanala – approx. 12 weeks from oral hearing (weeks 25)

Notice of the making of a Confirmation order – must be made within 12 weeks of the making of an order (weeks 24-37)

Period during which a judicial review can be sought – 8 weeks from notification (weeks 28-35)

Notice to treat – must be served within 18 months of confirmation of CPO