MOTION NO.7
MOTION: Councillor D. Looney
"That this Committee calls for the immediate roll-out of the flood alleviation scheme for the River Poddle, and requests a report with full details of the scheme since its initial inception."
REPORT:
River Poddle Flood Alleviation Scheme
Options for dealing with flood risk on the Poddle River were identified under the Eastern Catchment Flood Risk Assessment and Management (ECFRAM) study and consultations with the public took place in 2013. The preferred proposals for flood mitigation measures on the River Poddle include:
The proposed works for the overall scheme cross two Council boundaries and South Dublin County Council (SDCC) working in collaboration with Dublin City Council (DCC) will take the proposals forward through planning and eventual construction. Documents for the procurement of the design and environmental consultants for the Scheme are currently being finalised. The consultants will also prepare a detailed Cost Benefit Analysis for the proposed works.
The documents for the procurement of a consultant are informed by the Poddle Options Report which was produced by the OPW in July 2014. It was originally intended that SDCC would procure a design consultant and an environmental consultant from DCC’s existing framework in order to avoid having to tender from scratch. However following legal advice it was decided that DCC would invite tenders from their framework and that the design and environmental services would be merged into one brief for the procurement of one consultant. DCC are finalising the brief and they intend to invite tenders from consultants within the next few weeks.
The project involves an Environmental Impact Statement which requires public consultation and has to be submitted to An Bord Pleannala for approval.
It is intended to divide the scheme into two phases: the first phase is the works at Tymon Park and the second phase is the works downstream of Tymon Park.
Subject to the identification of an environmentally viable and cost beneficial scheme and successful completion of the planning process (including acquisition of land and wayleaves) it is hoped to be in a position to commence construction of the Tymon Park works in 2017 and the downstream works in 2018.
Construction of the works in Tymon Park will take about one year while construction of the remainder of the works will take about two years.
The Office of Public Works (OPW) has given a commitment, in principle, to funding a viable, cost beneficial and environmentally acceptable scheme for the Poddle and has made indicative provision for its cost in its Multi-Annual Capital Budget Profiles.
The works proposed to alleviate flooding on the Poddle are to be designed to the standard level of protection often referred to as the 100-year flood, which is to prevent flooding during events with a 1% annual exceedance probability (AEP) for fluvial floods. The design will take account also of climate change.
Interim works carried out to date by SDCC involve new debris screens placed on culverts on the river which are monitored remotely by telemetry. Any alarms can be responded to quickly so that debris build up can be removed in good time.