COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF SOUTH DUBLIN COUNTY COUNCIL

Monday, February 08, 2016

QUESTION NO.23

QUESTION: Councillor F. Timmons

To ask for a report into the reasons why no houses have been built 2013 to 2014 and how many in 2015 where built by SDCC and how many are envisaged to be built in 2016 ?

REPLY:

The following is a schedule of new build projects which commenced on site in 2015:

Scheme Address   Estimated Delivery   Date
Suncroft Tallaght 10 dwellings 2nd Quarter 2016
St Finians   2   dwellings 2nd Quarter 2016
Belgard Road   Tallaght (traveller accommodation)   3 dwellings 1st Quarter 2016
 Total 15  

The Office of Government Procurement is establishing a new framework for Consultants in respect of new build projects within specified financial thresholds; when this framework has been declared active (due to be finalised end January 2016) SDCC propose to go to tender in respect of the following projects, which have been Part V8 approved:

Scheme Address  
    St.        Marks Green
11 dwellings
      Mayfield       
18 dwellings
      Mac        Uilliam
28 dwellings 
  57

 

Progress on the rollout of the Part V Programme as reported to March 2015 Co. Co. Meeting is as follows: 

Scheme Name   (Location Address)   Approved by Council Current Stage
Dromcarra, Tallaght 14 Yes, June 2015 Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval
Letts Field,   Clondalkin 37  Yes,   September 2015 Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval
Owendoher,   Ballyboden 40  Yes, October 2015 Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval
Killinarden,   Tallaght 27 Yes, November 2015 Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval

The Council is unable to confirm estimated completion dates in respect of the above Part 8 projects pending receipt of budget cost approval from the Declg. The projects listed are in included in the SDCC Housing Strategy 2015-2017 new build programme.

The Part 8 programme will continue to progress on an incremental basis throughout the county. As part of the consultation process the Council is open to engaging with representative resident groups within the area of the proposed development.

The following additional sites identified for Part 8 will be displayed for public consultation over the coming months as follows:

Address  
Balgaddy ‘F’ Lucan 50
St Marks Avenue,Rowlagh 39
Stocking Lane,   Rathfarnham 40
Fernwood, Tallaght 22
Fonthill Road Link   Road, Neilstown 50
St. Aidans, Brookfield, Tallaght 50
Maplewood, Tallaght 18
  269

The numbers of homes above are indicative and may vary slightly as schemes are designed/amended following on the

public consultation process.