COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, February 08, 2016
QUESTION NO.23
QUESTION: Councillor F. Timmons
To ask for a report into the reasons why no houses have been built 2013 to 2014 and how many in 2015 where built by SDCC and how many are envisaged to be built in 2016 ?
REPLY:
The following is a schedule of new build projects which commenced on site in 2015:
Scheme Address | Estimated Delivery Date | |
Suncroft Tallaght | 10 dwellings | 2nd Quarter 2016 |
St Finians | 2 dwellings | 2nd Quarter 2016 |
Belgard Road Tallaght (traveller accommodation) | 3 dwellings | 1st Quarter 2016 |
Total | 15 |
The Office of Government Procurement is establishing a new framework for Consultants in respect of new build projects within specified financial thresholds; when this framework has been declared active (due to be finalised end January 2016) SDCC propose to go to tender in respect of the following projects, which have been Part V8 approved:
Scheme Address | |
|
11 dwellings |
|
18 dwellings |
|
28 dwellings |
57 |
Progress on the rollout of the Part V Programme as reported to March 2015 Co. Co. Meeting is as follows:
Scheme Name (Location Address) | Approved by Council | Current Stage | |
Dromcarra, Tallaght | 14 | Yes, June 2015 | Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval |
Letts Field, Clondalkin | 37 | Yes, September 2015 | Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval |
Owendoher, Ballyboden | 40 | Yes, October 2015 | Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval |
Killinarden, Tallaght | 27 | Yes, November 2015 | Full Cost plan submitted to DECLG - awaiting Pre-Tender Approval |
The Council is unable to confirm estimated completion dates in respect of the above Part 8 projects pending receipt of budget cost approval from the Declg. The projects listed are in included in the SDCC Housing Strategy 2015-2017 new build programme.
The Part 8 programme will continue to progress on an incremental basis throughout the county. As part of the consultation process the Council is open to engaging with representative resident groups within the area of the proposed development.
The following additional sites identified for Part 8 will be displayed for public consultation over the coming months as follows:
Address | |
Balgaddy ‘F’ Lucan | 50 |
St Marks Avenue,Rowlagh | 39 |
Stocking Lane, Rathfarnham | 40 |
Fernwood, Tallaght | 22 |
Fonthill Road Link Road, Neilstown | 50 |
St. Aidans, Brookfield, Tallaght | 50 |
Maplewood, Tallaght | 18 |
269 |
The numbers of homes above are indicative and may vary slightly as schemes are designed/amended following on the
public consultation process.