QUESTION: Councillor M. Genockey

"To ask the Chief Executive to give details on what work remains to be done on Carrigmore Park by the Council and if a timeframe can be given for this work to be completed?"

REPLY:

The remaining work to be completed at Carrigmore Park is essentially the undertaking of the remaining snag list. As most of this work is weather dependent it will be Spring 2016 before this is started.

Recent work in the park included the installation of lighting along the path from the Citywest Shopping Centre side to connect to Verschoyle and Saggart Abbey housing estates.