COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF HOUSING SPC
Thursday, November 12, 2015
HEADED ITEM NO.3
HEADED ITEM: M. Donovan
Social Housing progress update
REPLY:
Housing SPC Meeting
12th November 2015
H-I (3) - Housing Supply Progress Versus Targets South Dublin County Council is required to deliver 1445 Social Housing Units for the period 2015-2017. The targets were set under a combination of Capital and Current expenditure programmes. The below table outlines the targets for each mechanism for provision of social housing and the units delivered to the end of October 2015.
|
1. Social Housing Infill: 3 Construction Projects on site as at October 2015. 15 Units
The rollout of the Part 8 social housing developments are reported as follows:
Scheme Name (Location Address) | Approved by Council | Current Stage | |
Dromcarra, Tallaght | 14 | Yes in June 2015 | Cost plan submitted to DECLG for pre-tender approval |
Letts Field, Clondalkin | 37 | Yes September 2015 | Cost plan submitted to DECLG for pre-tender approval. |
Owendoher, Ballyboden | 40 | Yes October 2015 | Cost plan submitted to DECLG for pre-tender approval. |
Killinarden, Tallaght | 27 | Yes November 2015 | Cost plan will be submitted by end of November to DECLG for pre-tender approval. |
As presented to Council in March 2015 the further sites identified for Part 8 will display at consultation over the coming months:
Address | |
Balgaddy ‘F’ Lucan | 50 |
St. Marks Avenue, Clondalkin | 39 |
Stocking Lane, Rathfarnham | 40 |
Fernwood, Tallaght | 22 |
Fonthill Road Link Road, Neilstown | 50 |
The numbers of homes above are indicative and may vary slightly as schemes are designed and consulted in detail.
Three projects which have commenced on site in 2015 are:
|
10 dwellings |
|
2 dwellings |
|
3 dwellings |
Total | 15 |
Three projects are already Part 8 approved, costed and awaiting sanction to proceed to tender by DECLG - |
|
|
11 dwellings |
|
18 dwellings |
|
28 dwellings |
57 |