COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, June 08, 2015
QUESTION NO.17
QUESTION: Councillor D. Looney
To ask the Chief Executive for an update on social housing plans for the County, detailing the numbers of social homes planned for each electoral area, the size and type of homes planned, the processes by which these homes are to be provided, and to make a statement on the matter?
REPLY:
The report to the Council Meeting in March 2015 set out proposals for Social Housing units for the period 2015 to 2017 in line with the Housing strategy as set out in the Governments “Social Housing Strategy 2020 – Support, Supply and Reform” published late November 2014. The Programme envisages both new-build housing and a flexible range of supports to the private rental sector and the social housing sector. Nationally the Programme aspires to the construction of 35,000 new houses to address social housing need. The Councils target for 2015 - 2017 is 1,445 of which 350 units will be through capital projects including direct build, CAS projects, acquisitions and Part V.
Following a detailed study of infill sites owned by South Dublin County Council carried out in late 2014. These sites were reviewed under criteria of –
The roll-out of Part 8 display at consultation over the coming months as reported is as follows:
Month | Address | |
March | Dromcarra Drive, Tallaght | 20 |
April | Letts Field, Neilstown | 25 |
May | Balyboden | 35 |
June | Balgaddy ‘F’ Lucan | 50 |
July |
|
39 |
August | Kilinarden Tallaght | 24 |
September | Stocking Lane, Rathfarnham | 40 |
October | Fernwood, Tallaght | 22 |
November | Fonthill Road Link Road, Neilstown | 50 |
December January 2016 |
|
50 18 |
The numbers of homes above are indicative and may vary slightly as schemes are designed and consulted in detail. An overall working target of 647 dwellings , including larger schemes mentioned earlier and not listed will be pursued as the Councils immediate target.
Three projects are already tendered and in process of approval to go on site –
|
10 dwellings |
|
2 dwellings |
|
2 dwellings |
15 | |
Three projects are already Part 8 approved, costed and awaiting sanction to proceed to tender by DOELG - |
|
|
11 dwellings |
|
18 dwellings |
|
28 dwellings |
57 |
The Part 8 process on Dromcarra is completed and has started on the Letts Field proposal.
The Council is also working Approved Housing Bodies on CAS proposals submitted to the Department.