QUESTION: Councillor P. Gogarty
"To ask the Chief Executive to provide a timeframe for the commencement and duration of the €180,000 works budgeted for at Waterstown Park, Palmerstown and Griffeen Valley Park, Lucan respectively, including an indication of whether the Griffeen refurbishment will necessitate full or partial closure and if so, for how long?"
REPLY:
Both of these projects are at the design stage and it would be May 2015 at the earliest before a tender for them will be issued. In relation to the existing playground in Griffeen Valley: this will necessitate a complete closure of the facility and it is likely to be closed for at least 5 months.