MEETING OF CLONDALKIN AREA COMMITTEE

Wednesday, April 16, 2014

QUESTION NO. 5

QUESTION: Councillor T. Gilligan

To ask the Manager for an update on the hut in Clondalkin Leisure Centre, is the paint removed or is the hut being taken down also an update on the resurfacing of the car park in the leisure centre?

REPLY:

As reported to the March Meeting of the Clondalkin Area Committee, see below, a detailed list of works has been drawn up for the area in and around the lower car park. 

REPORT:

The following Table provides details of work undertaken and proposed at the Nangor Road Car Park at Clondalkin Park since the matter was reported on at the Clondalkin ACM in December 2013.

Item Description Status
1 Removal of leaves, litter and debris from the grass area on the left side of the entrance Complete
2 Removal of graffiti from the security cabin Necessity to retain hut is being review.  Option to remove is under consideration
3 Removal of graffiti from the walls in the car park Completed
4 Replanting a beech hedge against the wall between the Nangor Road pedestrian entrance and the security hut To be planted in late Autumn 2014
5 Repair stone kerbing /dwarf wall around the perimeter of the car park Vegetation removed from kerbing and reinstatement ongoing
6 Clean up base of shrubbery in the Nangor Road car park Complete
7 Selective thinning of trees at the bottle bank end of the car park Significant thinning complete.  Area to be landscaped and bollards installed
8 Remove 3 ESB poles behind the wall in the car park ESB contacted and requested to remove poles
9 Remove section of overgrown shrubbery on the left and right of the approach to the Camac River bridge Shrubbery pruned.  Roots to grub out.
10 Monitor condition of bring banks and dumping Bring Banks removed
11 Pruning of shrubbery on river bank west side of bridge over Camac River Complete
12 New section of railing to be fitted between Pitch and Putt Course wall and bridge railing (behind security hut) Railing to be fabricated
13 Remark parking spaces in car park Quotations to be sought
14 Upgrade vehicle entrance from Nangor Road Scheme to be prepared
15 Lighting in car park Assess current lighting to determine if work required
16 Signage Review to be carried out

The extensive range of work proposed will be carried out over the course of 2014.  As a significant amount of work involves the input from third parties it would be preferable to present a further report in May, subject to the members approval, to allow sufficient time to progress the various items. 

Works are continuing in this area and the removal of the old bridge hut is due to take place shortly. There are no proposals to resurface the car park at this time. A further update will be presented to the Members at the May Meeting of the Area Committee.