COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, July 09, 2012
QUESTION NO. 5
QUESTION: Councillor E. Higgins
To ask the Manager for an update on the installation of exercise trails throughout the County?
REPLY:
Installation of the bases for the equipment at the following locations was completed approximately two weeks ago.
The company have advised that they are expecting delivery of the first consignment of equipment in the third week of July and installation of equipment will commence on a countywide basis upon delivery. The second consignment was shipped on 26th June and will arrive in 4-6 weeks time, following which the remaining equipment will be installed.
It is expected that all of the equipment will be installed by the end of August/early September.