THE HOUSING CONSTRUCTION AND PROCUREMENT REPORT.
Schemes on Site
Taylors Lane.
7 x 3 bedroom, 2 x 4 bedroom, 2.5 storey houses - 9 Units
Work commenced July 2011. Anticipated duration of Contract is 50 working weeks.
Pearse Brothers Park/Palmer Park (22 existing units)
Tender recommendation for energy upgrade and refurbishment of apartments submitted to the DOEHLG for approval. It is intended that works will commence on site in 1st Quarter 2012.