To ask the Manager for an updated report on the taking-in-charge of Griffeen Glen Boulevard and Courtyard to advise on a likely date for completion of the taking-in-charge process?
REPLY:
We spoke with the Developer Newlyn construction on 23rd November regarding the completion of the outstanding defects. We have agreed to meet on site specifically during the next period of heavy rainfall in order to determine the precise location of the more serious ponding defects. Hopefully, Newlyn will agree to remedy these defects, if not we will have to make a claim on the Bond.