COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF RATHFARNHAM AREA COMMITTEE
Tuesday, October 11, 2011
HEADED ITEM NO. 5
REPORT ON HOUSING CONSTRUCTION PROGRAMME
Completions 2010
College Drive (Part V) - Fold Housing Association Units 23
Schemes on Site
Taylor's Lane 9
Units (7 x 3 bedroom, 2 x 4 bedroom, 2.5 storey houses)
Work commenced July 2011. Anticipated duration of Contract is 50 working weeks.
Pearse Brothers Park / Palmer Park 22 existing units
Tender documents being prepared for thermal improvement and upgrade works. It is intended to advertise tenders in 4th Quarter 2011 with a view to work commencing on site in 1st Quarter 2012.