QUESTION: Councillor W. Lavelle
To ask the Manager to provide a further detailed update on the council’s programme of repairs to badly-damaged red asphalt speed-ramps throughout the county including repairs carried out since the reply to my question at the September meeting; and to advise on a timeframe for the outstanding repairs?
REPLY:
Below is a an updated list of ramps that have already been repaired and those that are programmed to be completed by the end of 2011.
Palmerston Depot Area
Ramps already repaired in 2011
Mill Rd Saggart
St Johns Estate
Boot Rd
Green Isle Rd
Neilstown Rd
Ramps programmed to be repaired
Hillcrest (Work commencing week beginning 3rd Oct.)
Ballyowen Lane and Liffey Terrace (Work commencing week beginning 3rd Oct.)
Esker Lane (Work commencing week beginning 3rd Oct.)
Boherboy Rd
Garter Lane
Johnstown Rd
Lealand Estate (Work commencing week beginning 3rd Oct.)
Bawnogue Rd (Work commencing week beginning 3rd Oct.)
Woodford Clondalkin
Ballymount Depot Area
Ramps already repaired in 2011
Taylors Lane
Killinarden Rd
Fettercairn Rd
Belgard Rd
Limekiln Rd
Keadean Ave
Lugnaquilla Ave
Kippure Ave
Castletymon
In the light of the experience from last year, the Council is in discussions with the National Transport Authority and contractors with a view to revising the specification of materials to be used in the formation of all new ramps.