COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

south dublin county council crest

MEETING OF RATHFARNHAM AREA COMMITTEE

Tuesday, May 10, 2011

QUESTION NO. 19

QUESTION: Councillor E. Coburn

"To ask the Manager for an update on the result of the tender process for the Stocking Lane footpath/cycle track upgrade and to detail expected commencement date of this project?"

REPLY:

The contract has been awarded to Stanley Macadam Company Limited. Site works are due to commence in the week following the May bank holiday and are expected to be complete by August 2011.