Cathaoirleach's Business
"That this Committee discusses with the aid of an up to date report the consequences of the delay in completion of Boheryboy Water Scheme on Stocking lane road works - the subsequent delay in commencing the footpath on Stocking lane, and new bus Stop adjacent to the Heath, and to state when this work as previously outlined will be commenced/completed."
REPORT:
The Boherboy Water Scheme Civil Works Contract which was awarded to Pierse Contracting Ltd is 90% or more completed. The outstanding works are mainly at the two reservoir sites at Saggart and Kiltalown where the site works including roads, footpaths, landscaping and fencing still have to be started or finished. There are two short pieces of water main still to be laid at the bottom of Stocking Lane and in Citywest beside the Blessington Road and a number of tie-ins between the newly laid mains and the existing mains. All these new mains except the line to Newcastle from Saggart which is in service have to be cleaned and sterilised.
Pierse Contracting have gone into liquidation. The Council is looking at all options for the completion of the work. A team is in place to assess the implications and schedule the actions to be taken. A bond is in place and the Council is confident that the scheme will be completed though it will likely be behind schedule.