REPORT ON HOUSING CONSTRUCTION PROGRAMME:
COMPLETIONS 2008 NUMBER OF UNITS
Whitechurch Phase 4 26 Units handed over.
COMPLETIONS 2009 NUMBER OF UNITS
Whitechurch Phase 5 7 Units
Whitechurch Phase 4 3 Units & Community Centre
SCHEMES ON SITE
College Drive (Part V) 23 Units - Anticipated Completion date 1st Quarter 2010
Stocking Lane
(Part V-Voluntary Units) 40 Units - 20 ground floor apartments and 20 first floor / second floor apartments.
Anticipated handover date - 4th Quarter 2009
PART 8 PROCESS
Taylors Lane 9 Units - Scheme not to proceed to tender in 2009 due to funding constraints.
Stocking Lane (Phase 1) 24 Units – Project brief submitted to D.O.E for approval August 2008
TENDER APPROVED N/A