REPORT ON HOUSING CONSTRUCTION PROGRAMME.

COMPLETIONS 2008              NUMBER OF UNITS

Whitechurch Phase 4           26 Units handed over.

COMPLETIONS 2009                 NUMBER OF UNITS

Whitechurch Phase 5           7 Units

Whitechurch Phase 4 3 Units & Community Centre

SCHEMES ON SITE

College Drive                      23 Units - Anticipated Completion date 4th Quarter 2009 (21 x 1 bedroom, 2 x 3 bedroom)

 (Part V Voluntary)              Fold VHA

Stocking Lane

(Part V-Voluntary Units)       40 Units - 20 ground floor apartments and 20 first floor / second floor apartments.

Circle VHA                        (20 to be handed over 4th quarter 2009 & 20 in 1st quarter 2010) 

PART 8 PROCESS

Taylors Lane                        9 Units - Scheme not to proceed to tender in 2009 due to funding constraints.

Stocking Lane (Phase 1)       24 Units – Project brief submitted to D.O.E for approval August 2008

TENDER APPROVED             N/A