COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF RATHFARNHAM AREA COMMITTEE
Tuesday, September 15, 2009
HEADED ITEM NO. 13
Report on Housing Construction Programme
Completions 2008
Whitechurch Phase 4 (29 Units) 26 Units
Total 26 Units
Completions 2009
Whitechurch Phase 5 (7 Units) 7 Units handed over 23/07/2009
Community Centre Handed over 21/05/2009
Schemes on Site
Whitechurch Phase 4 3 Units - 2x4 beds 2 storey specially adapted/1x3 bed single storey specially adapted due September 2009
Stocking Lane (Part V - Voluntary Units) 40 Units - 20 ground floor apartments and 20 first floor / second floor apartments
(20to be handed over 4th quarter 2009 and 20 in 1st quarter 2010)
Total 43 Units
Part 8 Process
Taylor's Lane (9 Units) 9 Units - Project not to proceed to tender in 2009 due to funding constraints
Stocking Lane (Phase 1) 24 Units - Project brief submitted to the Department for approval August 2008
Tender Approved N/A