COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TERENURE-RATHFARNHAM AREA COMMITTEE (2)
Tuesday, April 07, 2009
HEADED ITEM NO. 6
Report on Housing Construction Programme
COMPLETIONS 2008 NUMBER OF UNITS
Whitechurch Phase 4 26 Units handed over.
SCHEMES ON SITE ANTICIPATED COMPLETION DATE:
Whitechurch Phase 4 3 Units to be handed in May 2009
Community Centre 1st Qtr 2009
Whitechurch Phase 5 7 Units April 2009
PART 8 PROCESS
Taylors Lane – DOE Approval to proceed to tender received 20 Jan 2009. Proceeding further will be dependant on 2009 DoEHLG Allocation due to be notified in coming weeks.
VOLUNTARY AND PART V: NUMBER OF UNITS
On site
College Drive 23
Not yet on site
Wainsfort Manor 51