Report on Housing Construction Programme
2008 COMPLETIONS TO DATE
Avonbeg Phase 3 29 units
Cushlawn Phase 3 22 units
Heatherset (Part V) 40 units
Ard Mor (Part V) 2 units
Kilcarrig / Drumcairn 34 units
TOTAL 127 UNITS
2009 COMPLETIONS TO DATE
Kiltalown 27 units
TOTAL 27 UNITS
SCHEMES ON SITE
Fortunestown B Phase 1 110 units (remedial works in progress on heating systems in 57 units)
Kilcarrig Phase 3 45 units 20 units in March / 25 units in April
Greenhills Road (Part V) 8 units 2nd Quarter 2009
Arena Court (Part V) 35 units 1st Quarter 2009
Eaton, Rathcoole (Part V) 4 units 2nd Quarter 2009
Avonbeg Phase 4 7 units 3rd Quarter 2009
Fettercairn Phase 2 32 units 3rd Quarter 2010
Castletymon 32 units 1st Quarter 2010
Stocking Lane (Part V) 40 units 4th Quarter 2009
TOTAL 313 UNITS
TENDER ASSESSMENT
Knockmore 90 units Approval received from DOE. Proposed start October 2009
Stocking Lane 24 units Project brief submitted to the Department for approval
Deerpark 8 units Target Tender date, 4th Quarter 2009
Rossfield Old Shop Site 9 units Target Tender 4th Quarter 2009
Fortunestown B Phase 3 & 5 160 units Proposal being reviewed by Architects Department
TOTAL 291 UNITS
CONCEPT DESIGN
Suncroft 10 units 2010 Start
TOTAL 10 UNITS