Report on housing construction programme
REPLY:
2008 COMPLETIONS TO DATE
SCHEME NO. OF UNITS
Avonbeg Phase 3 29
Cushlawn Phase 3 22
Heathersett 40
Ard Mor (Part V) 2
Kilcarrig/Drumcairn 34
TOTAL 127
SCHEMES ON SITE
Fortunestown B Phase 1 110 Conciliator appointed. Remedial works in progress on heating systems in 57 units.
Greenhills Road Part V 8 1st Quarter 2009
Kilcarrig Phase 3 45 21no in March and 24 no in April 2009
Kiltalown 27 End January / Early February 2009
Arena Court Part V 35 1st quarter 2009
Avonbeg Phase 4 7 3rd Quarter 2009
Fettercairn Phase 2 32 3rd Quarter 2010
Castletymon 32 1st Quarter 2010
TOTAL 297
TENDER ASSESSMENT
Fortunestown B Phase 3& 5 160 Proposal being reviewed by Architects Department
Rossfield Old Shop Site 9 Target tender
Knockmore 90 Tenders being assessed. Awaiting approval from the DOE.
Stocking Lane 100 New project brief submitted for 1st phase to be submitted to the Department for approval
Deerpark 8 Target tender date 1st quarter 2009
TOTAL 367
CONCEPT DESIGN
Suncroft 10 2009 start