2008 Completions to Date
Scheme No. of Units
Avonbeg Phase 3 29
Cushlawn Phase 3 22
Heathersett 40
Ard Mor (Part V) 2
Total 93
Schemes on Site
Fortunestown B Phase 1 110 Conciliator appointed
Remedial works in progress on
heating systems in 57 units
Greenhills Road Part V 9 1st Quarter 2009
Kilcarrig Phase 3 79 2 December 2008
Kilcarrig Green 5 3 January 2009
Killcarrig Green 22 End January 2009
Arena Court Part V 35 1st Quarter 2009
Avonbeg Phase 4 7 3rd Quarter 2009
Fettercairn Phase 2 32 3rd Quarter 2010
Castletymon 32 1st Quarter 2010
Total 331
Tender Assessment
Fortunestown B Phase 160 Proposal being
3 & 5 reviewed by Architects Dept.
Rossfield Old Shop Site 9 Target Tender date 1st
Quarter 2009
Knockmore 90 Tenders being assessed.
Awaiting approval from DOE.
Stocking Lane 100 Project brief submitted
to DOEHLG for approval
August 2008
Deerpark 8 Target tender date 1st
quarter 2009
Total 367
Concept Design
Suncroft 10 2009 start