COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE (1)
Monday, November 17, 2008
HEADED ITEM NO. 8
HEADED ITEM: H. Department
Report on housing construction programme
REPLY:
Completions to Date
Scheme No of Units
Avonbeg Phase 3 29
Cushlawn Phase 3 22
Heathersett 20
Ard Mor (Part V) 2
Total 73
_______________________________________________________________________________________
Schemes on Site
Fortunestown B Phase 1 110 Conciliator appointed. Remedial works in progress on heating systems in 57 units
Greenhills Road Part V 9 1st Quarter 2009
Kilcarrig Phase 3 80 34 homes due for completions November 2008 and remainder early 2009
Kiltalown Green 27 January 2009
Heathersett 20 4th Quarter 2008
Arena Court Part V 35 4th Quarter 2008
Avonbeg Phase 4 7 3rd Quarter 2009
Fettercairn Phase 2 32 3rd Quarter 2010
Castletymon 32 1st Quarter 2010
Total 352
_______________________________________________________________________
Tender Assessment
Fortunestown B Phase 3&5 160 Proposal being reviewed by Architects Department
Rossfield Old Shop site 9 Target Tender date 1st Quarter 2009
Knockmore 90 Tenders being assesed
Stocking Lane 100 project brief submitted August 2008 to DOEHLG for approval
Deerpark 8 Target tender date 1st Quarter 2009
Total 367
___________________________________________________________________________
Concept Design
Suncroft 10 2009 start
Total 10