COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE (1)
Monday, October 20, 2008
HEADED ITEM NO. 8
HEADED ITEM: H. Department
Report on housing construction programme
REPLY:
Completions 2004
Scheme No of Units
Cushlawn Ph1 2
Tymon Park 2
Bolbrook 11
Kilcarrig Ph2 8
Russell Square 5
Marlfield Part V 26
Total 54
Completions 2005
Scheme No of Units
Marfield Part V 1
Russell Square 110
Bawnlea 7
Jobstown Village Core 11
Cushlawn Ph2 31
Daletree Part V 8
Fettercairn Village 22
Total 190
Completions 2006
Scheme No of Units
Fettercairn Village 19
Deerpark Joint Venture 11
Fortunestown B Phase 2 38
Fortunestown B Phase 4 120
Daletree Part V 24
Total 212
Completions 2007
Scheme No of Units
Fortunestown B Phase 2 28
Daletree Part V 3
Brookfield 16
Castlepark 9
Deerpark Part V 36
Avonbeg 18
Heathersett 20
Total 130
Completions 2008 to Date
Scheme No of Units
Avonbeg Phase 3 29
Cushlawn Phase 3 22
Heathersett 20
Total 71
Schemes on Site
Scheme No of Units Remaining Comment
Fortunestown B Phase 1 110 Conciliator appointed. Remedial works in progress on heating systems in 57 units.
Greenhills Road Part V 9 4th Quarter 08
Kilcarrig Phase 3 80 34 homes due for completion in November 2008 and balance early 2009
Kiltalown Green 27 Jan-09
Ardmore Part V 2 4th Quarter 08
Heatherset 20 4th Quarter 08
Arena Court Part V 35 4th Quarter 08
Avonbeg Phase 4 7 3rd Quarter 2009
Fettercairn Phase 2 32 3rd Quarter 2010
Castletymon 32 1st Quarter 2010
Total 354
Tender Assessment
Scheme No of Units Comment
Fortunestown B Phase 3 / 5 160 Proposal being reviewed by Architects Dept
Rossfield Old Shop Site 9 Target Tender date 1st Quarter 2009
Knockmore 90 Tenders being assessed
Stocking Lane 100 Project brief submitted August 2008 to DoEHLG for approval
Deerpark 8 Target tender date 1st Qtr 2009
Total 367
Concept Design
Scheme No of Units Comment
Suncroft 10 2009 start
Total 10