COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE (2)
Monday, June 23, 2008
HEADED ITEM NO.H-1(3)
Taking in Charge of Estates – Roads & Services
The attached detailed listing sets out the up-to-date position on the taking in charge of developments.
To date one estate has been taken in charge in 2008
Taking in charge recommendations are being prepared in a further 8 cases.
The following is the up to date priority listing for the Tallaght area :-
o Daletree (Phase 1, 11A & 2)
o Ferncourt (Phase 1 & 2)
o Hunters Road/Oldcourt Road (road only)
o Kiltipper Way (road only)
o Mont Pelier
o Oak Dale
o Old Court
o Parklands (part of)
TALLAGHT AREA COMMITTEE
Meeting of the Tallaght Area Committee - 23rd JUNE 2008
Item No. H-I (3) - Taking in Charge Listing - Roads and Services
No. of Houses Estate Location Developer
Works Outstanding
A ESTATES TAKEN IN CHARGE IN 2008
448 Ellensborough Phases 1 - 4 Tallaght Durkan New Homes Ltd.
Taken in Charge on 14/01/2008
C ESTATES WHERE TAKING IN CHARGE RECOMMENDATIONS ARE BEING PREPARED:
283 Daletree (Phase 1, 1lA & 2) Ballycullen Maplewood Homes
TIC drawings and schedule being prepared.
To be recommended for TIC Autumn 2008.
176 Ferncourt (Phase 1 & 2) Ballycullen Maplewood Homes
TIC drawings and schedule being prepared.
To be recommended Autumn 2008.
0 Hunters Road/Oldcourt Road Ballycullen Ellier Development Ltd
Road only. To be recommended for TIC
Summer 2008.
0 Kiltipper Way Tallaght Durkan New Homes Ltd
TIC Schedule being prepared for Road at
Kiltipper Way, Tallaght from junction with
Whitestown Way (Road only) Works 90%
completed. Drawings being prepared.
50 Mont Pelier Jobstown Durkan New Homes Ltd.
"As constructed" drawings submitted and being
checked. Some works o/s. Drawings to be
prepared. To be recommended for TIC late
2008
177 Oak Dale Ballycullen Maplewood Homes
TIC drawings and schedule being prepared.
To be recommended for TIC Autumn 2008.
54 Old Court Ballycullen Maplewood Homes
TIC schedule and drawings being prepared.
To be recommended for TIC Autumn 2008
59 Parklands (part of) Ballycullen Maplewood Homes
Revised Drawings & CCTV requested and
awaited. Clarification of areas to be
TIC awaited.
C1 ESTATES WHERE ROADS ONLY - HAVE BEEN TAKEN IN CHARGE
498 Sundale (Phase 1 - 6) Tallaght Kelland Homes Ltd.
Roads TIC on 8th March, 2004 Services not
yet recommended for TIC. Drainage survey
and revised drawings submitted and being
checked.
D ESTATES WHERE TAKING IN CHARGE WORKS ARE STILL OUTSTANDING
290 Beechdale Ballycullen Maplewood Developments Ltd.
Mixed residential development.
(Partially private development). Management
Agreement submitted. Remedial works list
being prepared and issued. Drawings & CCTV
requested and awaiting.
187 Broadfield Manor Rathcooole Cavan Developments
List of remedial works prepared and issued.
Awaiting Drawings and CCTV. Remedial
works almost completed.
150 DeSelby Tallaght Kelland Homes Ltd.
Revised remedial list issued. Minor works
outstanding which include works to footpaths
and drainage. "As constructed" drawings and
drainage survey requested and awaited. Final
inspection to be carried out re remedial works
Awaiting CCTV.
230 Verschoyle (Phase 1) Saggart Kingscroft Developments
Works completed. "As constructed" drawings
and drainage survey submitted and being
checked. Drainage not to be TIC at present as
it drains into private drains.
F1 ESTATES SUBJECT TO LEGAL DIFFICULTIES:
40 Newhall Court, Blessington Road Jobstown William Smith
Enforcement proceedings regarding
outstanding works in Phase 1 adjourned -
awaiting confirmation of new Court date.
G ESTATES UNDER CONSTRUCTION:
655 Hunters Wood Ballycullen Ellier Developments Ltd.
Mixed Residential development. House
construction completed in phase 1. Partially
private. Remedial works prepared on 50% of
Estate. Awaiting "As constructed" drawings
and wayleaves for all 6 phases of
development. Phase 1 TIC works completed.
Phase 2 almost completed
260 Stocking Lane Rathfarnham Deane Homes
Mixed Residential development under
construction
H PRIVATE DEVELOPMENTS (NOT TO BE TAKEN IN CHARGE)
107 Blackthorn Hill Rathcoole Durkan New Homes Ltd.
Private development. House
construction complete. Remedial list being
prepared. 50% of remedial works done.
External footpaths only to be TIC
182 Dalriada Estate Ballycullen Ellier Development Ltd
Residential Development -
Construction ongoing.
594 Deerpark Kiltipper Durkan New Homes
Mixed residential development partially
private.
Management Agreement submitted.
Remedial works 80% completed.
24 Greenhills Court Tallaght John O'Connor
Apartments. Private development.
361 Marlfield Tallaght Durkan New Homes
Remedial works List prepared and issued.
Private Development. Works almost
completed. Drawings received and being
checked. External footpaths to be TIC.
325 Mill Race Saggart Neville Development Partnership
Phase 1 Mixed Residential Development -
House construction nearing completion -
Private. Management Agreement
submitted. Only main road & adjoining
footpath to be TIC. Drawings & CCTV
requested. Development to be re-inspected.
108 New Bancroft Tallaght Park Development
Apartment development.
Management Agreement submitted.
46 Parsons Court Newcastle Walsh Maguire & Co. Ltd
Private development consisting of 16 houses
and 30 apartments - Not for TIC.
Management Agreement submitted.
210 Priors Gate Tallaght P. Elliott
Apartment development .
Bridge to be TIC.
101 Saggart Green Saggart Melbury Developments Ltd
Apartment development
387 Tallaght Cross Tallaght Keenbury Properties Ltd.
Private development
Apartment and commercial development.
745 The Belfry City West Durkan New Homes/Hollioake
Mixed residential development. Partially
private. House construction almost complete,
Remedial work list prepared for whole of
estate. Management Agreement submitted.