REPLY:
| Completions 2004 | ||
| Scheme | No of Units | |
| Cushlawn Ph1 | 2 | |
| Tymon Park | 2 | |
| Bolbrook | 11 | |
| Kilcarrig Ph2 | 8 | |
| Russell Square | 5 | |
| Marlfield Part V | 26 | |
| Total | 54 | |
| Completions 2005 | ||
| Scheme | No of Units | |
| Marfield Part V | 1 | |
| Russell Square | 110 | |
| Bawnlea | 7 | |
| Jobstown Village Core | 11 | |
| Cushlawn Ph2 | 31 | |
| Daletree Part V | 8 | |
| Fettercairn Village | 22 | |
| Total | 190 | |
| Completions 2006 | ||
| Scheme | No of Units | |
| Fettercairn Village | 19 | |
| Deerpark Joint Venture | 11 | |
| Fortunestown B Phase 2 | 38 | |
| Fortunestown B Phase 4 | 120 | |
| Daletree Part V | 24 | |
| Total | 212 | |
| Completions 2007 | ||
| Scheme | No of Units | |
| Fortunestown B Phase 2 | 28 | |
| Daletree Part V | 3 | |
| Brookfield | 16 | |
| Castlepark | 9 | |
| Deerpark Part V | 36 | |
| Avonbeg | 18 | |
| Oldcourt/Heatherset/Hunterswood | 20 | |
| Total | 130 | |
| Completions 2008 to Date | ||
| Scheme | No of Units | |
| Avonbeg Phase 3 | 22 | |
| Cushlawn Phase 3 | 8 | |
| Total | 30 | |
| Schemes on Site | ||
| Scheme | No of Units Remaining | Comment |
| Fortunestown B Phase 1 | 110 | Conciliator appointed to resolve problem regarding heating in 57 units .South Dublin Council served notice to Ferrovial that remedial works will commence on 15/05/2008 |
| Avonbeg Phase 3 | 9 | Jun-08 |
| Cushlawn Phase 3 | 14 | Jul-08 |
| Greenhills Road Part V | 9 | 3rd Quarter 08 |
| Kilcarrig Phase 3 | 80 | 3rd Quarter 08 |
| Kiltalown Green | 27 | Jan-09 |
| Ardmore Part V | 2 | 3rd Quarter 08 |
| Oldcourt/Heatherset/Hunterswood | 20 | 3rd Quarter 08 |
| Arena Court Part V | 35 | 3rd Quarter 08 |
| Total | 306 | |
| Tender Assessment | ||
| Scheme | No of Units | Comment |
| Avonbeg Phase 4 | 7 | Anticipated start date 3rd Quarter 2008 |
| Fettercairn Phase 2 | 33 | Anticipated start date 3rd Quarter 2008 |
| Fortunestown B Phase 3 / 5 | 160 | Presently examined by Architects Dept |
| Castletymon | 32 | Tenders approved by DOEHLG |
| Rossfield Old Shop Site | 9 | Target Tender date 2nd Quarter 2008 |
| Knockmore | 96 | Tender advertised 30th May 2008 |
| Stocking Lane | 100 | Tender target preperation date 4th Qtr 2008 |
| Deerpark | 8 | Cost plan approved by DOE , tender documents being prepared , target tender date 3rd Qtr 2008 |
| Total | 445 | |
| Concept Design | ||
| Scheme | No of Units | Comment |
| Suncroft | 10 | Possible Affordable option.Concept to ACM on 19th Nov 07 |
| Total | 10 | |