Report on housing construction programme

REPLY:

REPLY:

Completions 2004    
Scheme No of Units  
Cushlawn Ph1 2  
Tymon Park 2  
Bolbrook 11  
Kilcarrig Ph2 8  
Russell Square 5  
Marlfield Part V 26  
Total 54  
     
Completions 2005    
Scheme No of Units  
Marfield Part V 1  
Russell Square 110  
Bawnlea 7  
Jobstown Village Core 11  
Cushlawn Ph2 31  
Daletree Part V 8  
Fettercairn Village 22  
Total 190  
     
Completions 2006    
Scheme No of Units  
Fettercairn Village 19  
Deerpark Joint Venture 11  
Fortunestown B Phase 2 38  
Fortunestown B Phase 4 120  
Daletree Part V 24  
Total 212  
     
Completions 2007    
Scheme No of Units  
Fortunestown B Phase 2 28  
Daletree Part V 3  
Brookfield 16  
Castlepark 9  
Deerpark Part V 36  
Avonbeg 18  
Oldcourt/Heatherset/Hunterswood 20  
Total 130  
     
Completions 2008 to Date    
Scheme No of Units  
Avonbeg Phase 3 22  
Cushlawn Phase 3 8  
Total 30  
     
Schemes on Site    
Scheme No of Units Remaining Comment
Fortunestown B Phase 1 110 Conciliator appointed to resolve problem regarding heating in 57 units .South Dublin Council served notice to Ferrovial that remedial works will commence on 15/05/2008
Avonbeg Phase 3 9 Jun-08
Cushlawn Phase 3 14 Jul-08
Greenhills Road Part V 9 3rd Quarter 08
Kilcarrig Phase 3 80 3rd Quarter 08
Kiltalown Green 27 Jan-09
Ardmore Part V 2 3rd Quarter 08
Oldcourt/Heatherset/Hunterswood 20 3rd Quarter 08
Arena Court Part V 35 3rd Quarter 08
Total 306  
     
Tender Assessment    
Scheme No of Units Comment
Avonbeg Phase 4 7 Anticipated start date 3rd Quarter 2008
Fettercairn Phase 2 33 Anticipated start date 3rd Quarter 2008
Fortunestown B Phase 3 / 5 160 Presently examined by Architects Dept
Castletymon 32 Tenders approved by DOEHLG
Rossfield Old Shop Site 9 Target Tender date 2nd Quarter 2008
Knockmore 96 Tender advertised 30th May 2008
Stocking Lane 100 Tender target preperation date 4th Qtr 2008
Deerpark 8 Cost plan approved by DOE , tender documents being prepared , target tender date 3rd Qtr 2008
Total 445  
     
Concept Design    
Scheme No of Units Comment
Suncroft 10 Possible Affordable option.Concept to ACM on 19th Nov 07
Total 10