COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE (1)
Monday, June 16, 2008
HEADED ITEM NO. 15
HEADED ITEM: H. Department
REPORT ON IMPLEMENTATION OF TRAVELLER ACCOMMODATION PROGRAMME
REPLY:
The following is the current position on developments at various stages of delivery throughout the Tallaght Area of the County.
Scheme | Type and No. of Units | Status | Comments |
Daletree Place | 10 Group Houses | Completed & Occupied | Residents moved into houses in August 2005. |
Belgard Park | 10 bay RCP | Completed & Occupied | Residents moved into houses in August 2005. |
St. Aidan’s Close Brookfield | 5 Group Houses | Completed & Occupied | Families moved in to houses on 3rd May 2006. |
Hazel Hill, Killinardin | Group Houses – 5 R.C.P. – 5 Bays | Completed & Occupied | Residents moved into scheme in December 2006. |
Fortunestown | 10 Group Houses – | Completed & Occupied | Residents moved into scheme in Dec. 2006. |
Stocking Lane | 10-bay RCP | Pre-construction | Works commenced delivery expected May 2009 |
Rathcoole | 10 GH | Pre-part 8 | Development delayed pending completion of roadworks. Pre-part 8 drawings being drafted |
Turnpike | 3 GH | Pre-part 8 | Part 8 procedure to commence June 2008 |
Belgard Road | 10 units | See report to this meeting |