COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

south dublin county council crest

MEETING OF SOUTH DUBLIN COUNTY COUNCIL

Monday, April 14, 2008

QUESTION NO. 6

QUESTION: Councillor C. King

To ask the Manager what percentage of the current Traveller Accommodation Programme has been implemented to date on a County-wide basis and is it envisaged the roll out of the programme will be completed within the life-time of the existing programme and can the manager make a statement on the matter?

REPLY:

The Assessment of need carried out in 2004 had indicated that a total of 215 units of accommodation would be required to provide for the current and future needs of the Traveller community within South Dublin County Council’s administrative area to the period to the end of 2008. The Traveller Construction Programme 2005 to 2008 has provided for the following units of accommodation through the construction phase of the accommodation programme :

1. Traveller Specific Developments      
Total No. of Traveller specific units to be provided in Programme = 215  
         
Electoral Area Location No. of Units Status Comments
Lucan Hayden's Lane 8 Completed Occupied April 2007
  Kishogue 20 On site Under Construction Delivery expected April 2008
  Fonthill Road 3 Part V Prices for units to be agreed
    3    
  Coldcut Road 8 Part V Contracts Signed - Construction to commence 2nd Quarter 2008
  Ballyowen Lane  5/6 Pre-part 8 All residents were interviewed during the conduction of the assessment and they have all indicated a preference for refurbishment rather than redevelopment
  Adamstown (1) 10 Part V Part of strategic development zone (SDZ)
  Adamstown (2)&(3) 20 Part V Part of strategic development zone (SDZ)
    69    
Electoral Area Location No. of Units Status Comments
Clondalkin Lock Road 6 Completed Family now resident on site
  Lock Road Permanent Site 6 Part 8 Part 8 process commenced
  Lynch's Lane 19 Contract signed Under construction - delivery October 2008
  3 Bay Emergency Site Lynchs Lane 3 Completed Occupied
  Tay Lane 7 Under Construction Under construction - Delivery April 2008
  Oldcastle Park 20   Phase 1 redevelopment at design stage
  Newcastle 10 Part 8 Under Construction - Delivery February 2009
  Bustyhill 10   Site to be identified.
    66    
Electoral Area Location No. of Units Status Comments
Tallaght Central Belgard Park 10 Completed Occupied May 2005
  Turnpike     Consultations held with residents Brief being prepared for Architects
  Belgard Road     Re-development of existing site dependent on ITT masterplan.
    10    
Electoral Area Location No. of Units Status Comments
Tallaght South Daletree Place 10 Completed Occupied August 2005
  St. Aidans 5 Completed Occupied May 2006
  Hazel Hill 10 Completed Occupied since 20th December 2006.
  Stocking Lane 10 Contract Construction  commenced - delivery April 2009
  Fortunestown 10 Completed Occupied in December 2006.
  Rathcoole 10   Awaiting completion of road infrastructure
  Brittas 10   Site to be identified.
  Blackchurch 5   Site to be identified.
    70    
         
  Total. 215    
         
  Total completed and occupied 53 24.65%  
         
  On Site 66 30.69%  
         
  To be on site by end 2008. 14 6.51%  

As well as this provision of Residential Caravan Park Bays and Group Housing schemes, the following are the numbers of Traveller families that have been provided social housing as their first choice of accommodation during the course of the Programme :

2. Standard Council Housing      
Total No. of Standard Units of Accommodation to be provided in Programme = 83 (21 Units per Annum)
        83
1 Traveller families housed in standard accommodaiton to end of January 2008 1%
36 Traveller families housed in standard accommodaiton to end of December 2007 43%
25 Traveller families housed in standard accommodation to end of December 2006 30%
16 Traveller families housed in standard accommodaiton to end of December 2005 19%
78 total housed in standard accommodation to end June 2007 94%

It is likely that the provision of social housing units will exceed the requirements set in the programme.

The Sites within the Programme that have not yet been given a start date are as follows :

SITE NAME                                                    COMMENTS.

Belgard Road.                                      The redevelopment of this site was considered to

                                                            commence in 2008, however due to the protracted

                                                            negotiations with the ITT, it is now unlikely to

                                                            commence this year.

Ballyowen Lane                                    The redevelopment of this site was to commence

                                                            2007/2008, however the residents, following a

                                                            consultation process, have indicated that they wish

                                                            only a refurbishment of this site now.

Adamstown 1, 2 and 3             These sites will be the subject of Part V discussions

                                                            with the relevant developers on site.

Rathcoole                                             Delays with the provision of the infrastructure has

                                                            meant the indefinite delay of the provision of this

                                                            site.

Bustyhill, Brittas, and

Blackchurch.                                        No sites have been identified yet.