COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, April 14, 2008
QUESTION NO. 6
QUESTION: Councillor C. King
To ask the Manager what percentage of the current Traveller Accommodation Programme has been implemented to date on a County-wide basis and is it envisaged the roll out of the programme will be completed within the life-time of the existing programme and can the manager make a statement on the matter?
REPLY:
The Assessment of need carried out in 2004 had indicated that a total of 215 units of accommodation would be required to provide for the current and future needs of the Traveller community within South Dublin County Council’s administrative area to the period to the end of 2008. The Traveller Construction Programme 2005 to 2008 has provided for the following units of accommodation through the construction phase of the accommodation programme :
1. Traveller Specific Developments | ||||||
Total No. of Traveller specific units to be provided in Programme = 215 | ||||||
Electoral Area | Location | No. of Units | Status | Comments | ||
Lucan | Hayden's Lane | 8 | Completed | Occupied April 2007 | ||
Kishogue | 20 | On site | Under Construction Delivery expected April 2008 | |||
Fonthill Road | 3 | Part V | Prices for units to be agreed | |||
3 | ||||||
Coldcut Road | 8 | Part V | Contracts Signed - Construction to commence 2nd Quarter 2008 | |||
Ballyowen Lane | 5/6 | Pre-part 8 | All residents were interviewed during the conduction of the assessment and they have all indicated a preference for refurbishment rather than redevelopment | |||
Adamstown (1) | 10 | Part V | Part of strategic development zone (SDZ) | |||
Adamstown (2)&(3) | 20 | Part V | Part of strategic development zone (SDZ) | |||
69 | ||||||
Electoral Area | Location | No. of Units | Status | Comments | ||
Clondalkin | Lock Road | 6 | Completed | Family now resident on site | ||
Lock Road Permanent Site | 6 | Part 8 | Part 8 process commenced | |||
Lynch's Lane | 19 | Contract signed | Under construction - delivery October 2008 | |||
3 Bay Emergency Site Lynchs Lane | 3 | Completed | Occupied | |||
Tay Lane | 7 | Under Construction | Under construction - Delivery April 2008 | |||
Oldcastle Park | 20 | Phase 1 redevelopment at design stage | ||||
Newcastle | 10 | Part 8 | Under Construction - Delivery February 2009 | |||
Bustyhill | 10 | Site to be identified. | ||||
66 | ||||||
Electoral Area | Location | No. of Units | Status | Comments | ||
Tallaght Central | Belgard Park | 10 | Completed | Occupied May 2005 | ||
Turnpike | Consultations held with residents Brief being prepared for Architects | |||||
Belgard Road | Re-development of existing site dependent on ITT masterplan. | |||||
10 | ||||||
Electoral Area | Location | No. of Units | Status | Comments | ||
Tallaght South | Daletree Place | 10 | Completed | Occupied August 2005 | ||
St. Aidans | 5 | Completed | Occupied May 2006 | |||
Hazel Hill | 10 | Completed | Occupied since 20th December 2006. | |||
Stocking Lane | 10 | Contract | Construction commenced - delivery April 2009 | |||
Fortunestown | 10 | Completed | Occupied in December 2006. | |||
Rathcoole | 10 | Awaiting completion of road infrastructure | ||||
Brittas | 10 | Site to be identified. | ||||
Blackchurch | 5 | Site to be identified. | ||||
70 | ||||||
Total. | 215 | |||||
Total completed and occupied | 53 | 24.65% | ||||
On Site | 66 | 30.69% | ||||
To be on site by end 2008. | 14 | 6.51% | ||||
As well as this provision of Residential Caravan Park Bays and Group Housing schemes, the following are the numbers of Traveller families that have been provided social housing as their first choice of accommodation during the course of the Programme :
2. Standard Council Housing | ||||
Total No. of Standard Units of Accommodation to be provided in Programme = 83 (21 Units per Annum) | ||||
83 | ||||
1 | Traveller families housed in standard accommodaiton to end of January 2008 | 1% | ||
36 | Traveller families housed in standard accommodaiton to end of December 2007 | 43% | ||
25 | Traveller families housed in standard accommodation to end of December 2006 | 30% | ||
16 | Traveller families housed in standard accommodaiton to end of December 2005 | 19% | ||
78 | total housed in standard accommodation to end June 2007 | 94% | ||
It is likely that the provision of social housing units will exceed the requirements set in the programme.
The Sites within the Programme that have not yet been given a start date are as follows :
SITE NAME COMMENTS.
Belgard Road. The redevelopment of this site was considered to
commence in 2008, however due to the protracted
negotiations with the ITT, it is now unlikely to
commence this year.
Ballyowen Lane The redevelopment of this site was to commence
2007/2008, however the residents, following a
consultation process, have indicated that they wish
only a refurbishment of this site now.
Adamstown 1, 2 and 3 These sites will be the subject of Part V discussions
with the relevant developers on site.
Rathcoole Delays with the provision of the infrastructure has
meant the indefinite delay of the provision of this
site.
Bustyhill, Brittas, and
Blackchurch. No sites have been identified yet.