COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TERENURE-RATHFARNHAM AREA COMMITTEE (2)
Tuesday, April 08, 2008
HEADED ITEM NO 2.
Report on housing construction programme
REPLY:
The up-to-date position of the Housing Construction Programme for the Terenure - Rathfarnham Area is set out in the detail below:-
COMPLETIONS 2004
Whitechurch Phase 3
Number of Units : 9
COMPLETIONS 2005
Whitechurch Phase 3
Number of Units: 10
SCHEMES ON SITE ANTICIPATED COMPLETION DATE
Whitechurch Phase 4
Anticipated Completion Dates :
8 units to be handed over 2nd April 2008.
Other 21 units to be handed over till end of June 2008.
Community Centre 2nd Qtr 2008,
Whitechurch Phase 5
Anticipated Completion Date: 7 units 12th May 2008
TENDER APPROVED:
N/A
PART 8 PROCESS:
Taylors Lane - Report approved at December County Council Meeting. Cost Plan submitted to DOE March 2008.