QUESTION NO. 12

QUESTION: Councillor E. Tuffy

To ask the Manager if he will provide an updated report on the Council's Six Year Roads Programme as set out in the County Development Plan 2005-2010?

REPLY:

REPLY:

The current position with regard to the Six Year Road objectives as set out in the County Development Plan is set out below:

6 Yrs. Road Objective Planning Stage Design Stage Under Construction Constructed
M50 Upgrade     X  
N4 Upgrade (M50 Junction to M4)     X  
N7 Upgrade, (Rathcoole – Co. Boundary)       X
N81 Blessington Road (Ext. of the Tallaght By-Pass) X      
Firhouse Road from Ballycullen Road to Old Bawn Road     X  
Green Route: Taylor’s Lane (Boden Park) to Grange Road     X  
Greenhills Road to Ballymount Road Lower to Longmile Road (Part of)   X    
Knocklyon Road to Firhouse Road   X    
City West to Belgard Road (Embankment Route)   X    
Walkinstown Roundabout to Calmount Road X      
Adamstown Roundabout ORR to the N4       X
Adamstown Roundabout ORR to Fonthill Road Link       X
Adamstown Link Road from ORR to SDZ Lands       X
Adamstown SDZ to Celbridge Road X      
Lucan/Newcastle Road at Finnstown       X
Outer Ring Road (N7 Kingswood Interchange to the N81)     X  
Fortunestown Lane to City West (Completion of)     X  
Ballycullen/Oldcourt Stocking Lane Road Network       X
Newcastle Road (Local Area Plan)     X  
Nangor Road Estension from Grange Castle to the Lucan/Newcastle Road (R120) and south from new junction to Pollyhops with link to Baldonnell Road   X    
Adamstown SDZ Internal Roads     X  
Cookstown Road (rear of Fortunestown Local Centre)     X  
Greenhills Road to Limekiln Road    X    
Esker Lane X      
Barton Road East Extension X      
Barneys Lane to City West Interchange X      
Saggart Road (Local Area Plan)     X  
Rathcoole (Local Area Plan) X      
Upgrade junctions in Glenasmole/Bohernabreena Housing and Planning Study area. X      

Progress on the six year road programme set out in the County Development Plan 2005-2010 is dependent on the availability of the necessary financial resources.