COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

south dublin county council crest

MEETING OF TALLAGHT AREA COMMITTEE 2

Monday, February 25, 2008

HEADED ITEM NO.(H-1(03)

 

The attached detailed listing sets out the up-to-date position on the taking in charge of developments. 

Four estates were taken in charge in 2007.  To date one estate has been taken in charge in 2008

Taking in charge recommendations are being prepared in a further 8 cases.

The following is the up to date priority listing for the Tallaght  area :-

o         Daletree (Phase 1, 11A & 2)

o         Ferncourt (Phase 1 & 2)

o         Hunters Road/Oldcourt Road (road only)

o         Kiltipper Way  (road only)

o         Mont Pelier

o         Oak Dale

o         Old Court

o         Parklands (part of)


 

TALLAGHT AREA COMMITTEE

  Meeting of the Tallaght Area Committee -  25th  February 2008

  Item No.  H-I (3 ) - Taking in Charge Listing - Roads and Services

No. of Houses      Estate                                                           Location             Developer

                            Works Outstanding

A           ESTATES TAKEN IN CHARGE IN 2007

         11              Castlefield Orchard                                        Knocklyon           Brian Durkan & Co. Ltd

                            TIC on 08/10/2007

         97              Hazelgrove                                                     Tallaght               Kelland Homes Ltd.

                            Taken in Charge on 10/04/2007

           0              Oldcourt Distributor Road                               Stocking Avenue,       Oldcourt Developments

                            Distributor Road. Taking in Charge on 8th

                            October, 2007

       130              Swiftbrook                                                      Tallaght               Kelland Homes Ltd.

                            Taken in Charge 14-05-07

A2         ESTATES TAKEN IN CHARGE IN 2008

       448              Ellensborough  Phases 1 - 4                          Tallaght               Durkan New Homes Ltd.

                            Taken in Charge on 14/01/2008

C           ESTATES WHERE TAKING IN CHARGE RECOMMENDATIONS ARE BEING PREPARED:

       283              Daletree (Phase 1, 1lA & 2)                            Ballycullen           Maplewood Homes

                            TIC drawings and schedule being prepared. To

                            be recommended for TIC early 2008.

       176              Ferncourt (Phase 1 & 2)                                 Ballycullen           Maplewood Homes

                            TIC drawings and schedule being prepared. To

                            be recommended early 2008.

           0              Hunters Road/Oldcourt Road                         Ballycullen           Ellier Development Ltd

                            Road only. To be recommended for TIC  early

                             2008

           0              Kiltipper Way                                                  Tallaght               Durkan New Homes Ltd

                            TIC Schedule being prepared for Road at

                            Kiltipper Way, Tallaght from junction with

                            Whitestown Way (Road only) Works 90%

                            completed. Drawings being prepared.

         50              Mont Pelier                                                     Jobstown            Durkan New Homes Ltd.

                            "As constructed" drawings submitted and being

                             checked. To be recommended for TIC early

                            2008

       177              Oak Dale                                                        Ballycullen           Maplewood Homes

                            TIC drawings and schedule being prepared. To

                            be recommended early 2008

         54              Old Court                                                       Ballycullen           Maplewood Homes

                            TIC schedule and drawings being prepared. To

                            be recommended early 2008

         59              Parklands (part of)                                         Ballycullen           Maplewood Homes

                            Revised Drawings & CCTV requested and

                            awaiting.  Awiting clarification of areas to be

                            TIC

C1         ESTATES WHERE ROADS ONLY - HAVE BEEN TAKEN IN CHARGE

       498              Sundale (Phase 1 - 6)                                    Tallaght               Kelland Homes Ltd.

                            Roads TIC on  8th March, 2004  Services not

                            yet recommended for TIC. Drainage survey

                            and revised drawings submitted and being

                            checked.

D           ESTATES WHERE TAKING IN CHARGE WORKS ARE STILL OUTSTANDING

       187              Broadfield Manor                                            Rathcooole          Cavan Developments

                            List of remedial works prepared and issued.  

                            Awaiting Drawings and CCTV.  Remedial

                            works 95% complete.

       150              DeSelby                                                          Tallaght               Kelland Homes Ltd.

                            Revised remedial list issued. Minor works

                            outstanding which include works to footpaths

                            and drainage. "As constructed" drawings and

                            drainage survey requested and awaited. Final

                            inspection to be carried out.  Remedial works

                            98% completed.

           4              Sylvan Avenue                                               Kingswood          Mondale Const. Ltd.

                            Outstanding issues regarding drainage.  TIC

                            drawings being prepared.

       230              Verschoyle (Phase 1)                                     Saggart               Kingscroft Developments

                            Works completed.  "As constructed" drawings

                            and drainage survey submitted and being

                            checked. Drainage not to be TIC at present at

                            it drains into private drains.

F1         ESTATES SUBJECT TO LEGAL DIFFICULTIES:

         40              Newhall Court, Blessington Road                   Jobstown            William Smith

                            Enforcement proceedings regarding

                            outstanding works in Phase 1 adjourned -

                            awaiting confirmation of Court date

G           ESTATES UNDER CONSTRUCTION:

       655              Hunters Wood                                                Ballycullen           Ellier Developments Ltd.

                            Mixed Residential development. House

                            construction completed in phase 1. Partially

                            private. Remedial works prepared on 50% of

                            Estate. Awaiting "As constructed" drawings

                            and wayleaves for all 6 phases of

                            development.  Phase 1 TIC works completed.

                             Phase 2- 98% completed

       260              Stocking Lane                                                Rathfarnham       Deane Homes

                            Mixed Residential development under

                            Construction

H           PRIVATE DEVELOPMENTS (NOT TO BE TAKEN IN CHARGE)

       290              Beechdale                                                      Ballycullen           Maplewood Developments Ltd.

                            Mixed residential development. House

                            construction almost complete. (Partially

                            private development)  Management

                            Agreement submitted. Remedial works list

                            being prepared and issued.  Drawings & CCTV

                            requested and awaiting.

       114              Blackthorn Hill                                                Rathcoole            Durkan New Homes Ltd.

                            Mostly private development. House

                            construction complete. Remedial list being

                            prepared. 50% of remedial works done.

       594              Deerpark                                                        Kiltipper              Durkan New Homes

                            Mixed residential development partially

                            private.  (325 private & affordable units).

                            Management Agreement submitted. Remedial

                            works to be rechecked.

         24              Greenhills Court                                             Tallaght               John O'Connor

                            Apartments. Private development under

                            construction

       361              Marlfield                                                         Tallaght               Durkan New Homes

                            Mixed residential development. House

                            construction ongoing. Mostly private.   Only

                            some footpaths to be Taken in Charge.

                            Remedial works List prepared and issued.

                            Private Development. Works almost

                            completed.  Drawings received and being

                            checked. External and adajacnt footpaths to

                            be TIC.

       325              Mill Race                                                         Saggart               Neville DevelopmentPartnership

                            Phase 1 Mixed Residential Development -

                            House construction nearing completion -

                            mostly private. Management Agreement

                            submitted.  Only main road & adjoing

                            footpath to be TIC.  Drawings & CCTV

                            requested. Development to be re -inspected

       108              New Bancroft                                                 Tallaght               Park Developments

                            Apartments. Private development.

                           

       210              Priors Gate                                                     Tallaght               P. Elliott

                            Apartments. Private development.

                          Request to take bridge in charge.

                           

       101              Saggart Green                                               Saggart               Melbury Developments Ltd

                            Private apartment development.

       387              Tallaght Cross                                                Tallaght               Keenbury Properties Ltd.

                            Apartments. Private development.

                            387 apartments in mixed use

                            development

       745              The Belfry                                                       City West            Durkan New Homes/Hollioake

                            Mixed residential development.  Partially

                            private. 

                            Remedial work  list prepared for whole of

                            estate.  Management agreement submitted

       124              Westend Gate                                                Tallaght               Glan Developments