The following is the current position on developments at various stages of delivery throughout the Tallaght Area of the County.
| Scheme | Type and No. of Units | Status | Comments |
| Daletree Place | 10 Group Houses | Completed & Occupied | Residents moved into houses in August 2005. |
| Belgard Park | 10 bay RCP | Completed & Occupied | Residents moved into houses in August 2005. |
| St. Aidan’s Close Brookfield | 5 Group Houses | Completed & Occupied | Families moved in to houses on 3rd May 2006. |
| Hazel Hill, Killinardin | Group Houses – 5 R.C.P. – 5 Bays | Completed & Occupied | Residents moved into scheme in December 2006. |
| Fortunestown | 10 Group Houses – | Completed & Occupied | Residents moved into scheme in Dec. 2006. |
| Stocking Lane | 10-bay RCP | Pre-construction | Works commenced delivery expected May 2009 |
| Rathcoole | 10 GH | Pre-part 8 | Design for revised Part 8 process for group housing to be prepared. Discussions with future residents being held |
| Turnpike | 3 GH | Pre-part 8 | Consultations held with residents = pre part 8 drawings being prepared |
| Belgard Road | 10 units | Awaiting outcome of ITT plan |