The following is the current position on developments at various stages of delivery throughout the Tallaght Area of the County.
Scheme
Type and No. of Units
Status
Comments
Daletree Place
10 Group Houses
Completed & Occupied
Residents moved into houses in August 2005.
Belgard Park
10 bay RCP
Completed & Occupied
Residents moved into houses in August 2005.
St. Aidan’s Close Brookfield
5 Group Houses
Completed & Occupied
Families moved in to houses on 3rd May 2006.
Hazel Hill, Killinardin
Group Houses – 5 R.C.P. – 5 Bays
Completed & Occupied
Residents moved into scheme in December 2006.
Fortunestown
10 Group Houses –
Completed & Occupied
Residents moved into scheme in Dec. 2006.
Stocking Lane
10-bay RCP
Pre-construction
Works commenced delivery expected May 2009
Rathcoole
10 GH
Pre-part 8
Design for revised Part 8 process for group housing to be prepared. Discussions with future residents being held
Turnpike
3 GH
Pre-part 8
Consultations held with residents = pre part 8 drawings being prepared
Belgard Road
10 units
Awaiting outcome of ITT plan