COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TERENURE-RATHFARNHAM AREA COMMITTEE 2
Tuesday, December 11, 2007
HEADED ITEM NO. 3
Report on housing construction programme
The up-to-date position of the Housing Construction Programme for the Terenure - Rathfarnham Area is set out in the detail below:-
COMPLETIONS 2004
Whitechurch Phase 3
Number of Units : 9
COMPLETIONS 2005
Whitechurch Phase 3
Number of Units: 10
SCHEMES ON SITE ANTICIPATED COMPLETION DATE
Whitechurch Phase 4
Anticipated Completion Date : 29 units in phases from January 2008 & Community Facility
Whitechurch Phase 5
Anticipated Completion Date: 7 units January 2008
TENDER APPROVED
N/A
PART 8 PROCESS
Taylors Lane - Report presented to Terenure Rathfarnham Area Committee meeting November 2007 and the December County Council Meeting.