COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE 1
Monday, December 03, 2007
HEADED ITEM NO. 10
Report on Housing Construction Programme
Completions 2004
Cushlawn (Phase 1) - 28
Tymon Park - 2
Bolbrook - 11
Kilcarrig (Phase 2) - 8
Russell Square - 5
Marlfield (Part V) - 26
Total 80
Completions 2005
Marlfield (Part V) - 1
Russell Square - 110
Bawnlea - 7
Jobstown Village Core - 11
Cushlawn (Phase 2) - 31
Daletree(Part V) - 8
Fettercairn Village -22
Total - 190
Completions 2006
Fettercairn Village - 19
Deerpark Joint Venture - 11
Fortunestown B (Phase 2) - 38
Fortunestown B (Phase 4) - 120
Daletree (Part V) - 24
Total - 320
Completions 2007
Fortunestown B (Phase 2) - 28
Daletree (Part V) - 3
Brookfield - 16
Castlepark - 9
Total - 56
Schemes in progress - anticipated completion date
Fortunestown B (Phase 1 - 110 units) - In phasesearly 2008
Avonbeg (Phase 3 - 47 units) - 14 units to be handed over 5th December 2007, rest early 2008
Deerpark (Part V - 36 units) - early 2008
Cushlawn (Phase 3 - 22 units) - 1st Qtr 2008
Greenhills Road (Part V - 9 units) - 1st Qtr 2008
Kilcarrig (Phase 3 - 80 units) - 4th Qtr 2008
Kiltalown Green (27 units) - 3rd Qtr 2008
Ardmore (Part V - 2 units) - 2nd Qtr 2008
Total - 333 units
Tender Assessment
Avonbeg (Phase 4 - 7 units) - Anticipated start date 1st Qtr 2008
Fettercairn (Phase 2 - 33 units) - Anticipated start date 1st Qtr 2008
Comments
Fortunestown B (Phase 3 & 5 - 160 units) - tender being assessed
Castletymon (32 units) - tenders being assessed
Rossfield Old Shop Site (9 units) - Target tender 1s Qtr 2008
Knockmore (96 units) - Target tender 1st Qtr 2008
Stocking Lane (100 units) - Target tender date 2nd Qtr 2008
Deerpark (8 units) - cost plan to DOE
Total - 445
Concept/Design Stage
Suncroft (10 units) - possible affordable option - concept to ACM on 19th Nov 07
Swiftbrook (11 units) - concept to ACM 8th Dec 2004
Total - 21
Other potential sites are also being examined.