MEETING OF TALLAGHT AREA COMMITTEE 1
Monday, November 19, 2007
HEADED ITEM NO. 3
HEADED ITEM: H. Department
Report on housing construction programme
REPLY:
COMPLETIONS 2004
Cushlawn Phase 1 28
Tymon Park 2
Bolbrook11
Kilcarrig Phase 28
Russell Square5
Marlfield Part V 26
TOTAL 80
COMPLETIONS 2005
Marlfield Part V 1
Russell Square 110
Bawnlea 7
Jobstown Village Core 11
Cushlawn Phase 2 31
Daletree Part V 8
Fettercairn Village 22
TOTAL190
COMPLETIONS 2006
Fettercairn Village 19
Deerpark Joint Venture 119
Fortunestown B (Phase 2) 38
Fortunestown B (Phase 4) 120
Daletree Part V 24
TOTAL 320
COMPLETIONS 2007
Fortunestown B (Phase 2) 28
Daletree 3
Heathersett 20
Brookfield 16
Castlepark 3
TOTAL 70
SCHEMES IN PROGRESS ANTICIPATED COMPLETION DATE
Fortunestown B Phase 1 (110) In Phases December 2007 early 2008
Avonbeg Phase 3 (47) in Phases from December 2007 early 2008
Heathersett Part V (20) 1st quarter 2008
Deerpark Part V (36) December 2007
Castlepark (7) November 2007
Cushlawn Phase 3 (22) in Phases from December 2007
Greenhills Road Part V (9) December 2007
Kilcarrig Phase 3 (80) 4th Quarter 2008
Kiltalown Green (27) 3rd Quarter 2008
Ard Mor Part V (2) 1st Quarter 2008
TOTAL 360
TENDER ASSESSMENT
Avonbeg Phase 4 (7) Anticipated start date 1st quarter 2008
Fettercairn Phase 2 (33) Anticipated start date 1st quarter 2008
COMMENTS
Fortunestown Phase 3 & 5 (160) Tenders being assessed
Castle Tymon (32) Tenders being assessed
Rossfield Old Shop SIte (9) Target Tender 1st quarter 2008
Knockmore (96) Target Tender 1st quarter 2008
Stocking Lane (103) Target Tender 2nd quarter 2008
Deerpark (8) Cost plan with DOE
TOTAL 448
CONCEPT / DESIGN STAGE
Suncroft 10- possible affordable option. Concept to ACM 19/11/2007
Swiftbrook 11. COncept to ACM 08/12/2004
TOTAL 21
Other potential sites are also being examined