Report on housing construction programme

REPLY:

COMPLETIONS 2004

Cushlawn Phase 1 28

Tymon Park 2

Bolbrook11

Kilcarrig Phase 28

Russell Square5

Marlfield Part V 26

TOTAL 80

COMPLETIONS 2005

Marlfield Part V 1

Russell Square 110

Bawnlea 7

Jobstown Village Core 11

Cushlawn Phase 2 31

Daletree Part V 8

Fettercairn Village 22

TOTAL190

COMPLETIONS 2006

Fettercairn Village 19

Deerpark Joint Venture 119

Fortunestown B (Phase 2) 38

Fortunestown B (Phase 4) 120

Daletree Part V 24

TOTAL 320

COMPLETIONS 2007

Fortunestown B (Phase 2) 28

Daletree 3

Heathersett 20

Brookfield 16

Castlepark 3

TOTAL 70

SCHEMES IN PROGRESS ANTICIPATED COMPLETION DATE

Fortunestown B Phase 1 (110) In Phases December 2007 early 2008

Avonbeg Phase 3 (47) in Phases from December 2007 early 2008

Heathersett Part V (20) 1st quarter 2008

Deerpark Part V (36) December 2007

Castlepark (7) November 2007

Cushlawn Phase 3 (22) in Phases from December 2007

Greenhills Road Part V (9) December 2007

Kilcarrig Phase 3 (80) 4th Quarter 2008

Kiltalown Green (27) 3rd Quarter 2008

Ard Mor Part V (2) 1st Quarter 2008

TOTAL 360

TENDER ASSESSMENT

Avonbeg Phase 4 (7) Anticipated start date 1st quarter 2008

Fettercairn Phase 2 (33) Anticipated start date 1st quarter 2008

COMMENTS

Fortunestown Phase 3 & 5 (160) Tenders being assessed

Castle Tymon (32) Tenders being assessed

Rossfield Old Shop SIte (9) Target Tender 1st quarter 2008

Knockmore (96) Target Tender 1st quarter 2008

Stocking Lane (103) Target Tender 2nd quarter 2008

Deerpark (8) Cost plan with DOE

TOTAL 448

CONCEPT / DESIGN STAGE

Suncroft 10- possible affordable option. Concept to ACM 19/11/2007

Swiftbrook 11. COncept to ACM 08/12/2004

TOTAL 21

Other potential sites are also being examined