COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE 2
Monday, October 22, 2007
QUESTION NO. 4
QUESTION: Councillor E. Maloney
"To ask the manager when the rebuilding of the footbridge over the N81 between St Dominic's and Tallaght Village with be completed and will he make a statement on the matter?"
REPLY:
The developer has confirmed the following time scale for the completion of the footbridge (these dates are weather dependent):
·Bridge structure complete by Thursday, 25th October 2007.
·Waterproofing works (dry weather only) to commence from Wednesday, 24th October 2007.
·Bridge available to be open to the Public from Friday, 2nd November 2007.
·Removal of temporary bridge to commence from Monday 5th November 2007.