COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

south dublin county council crest

MEETING OF TALLAGHT AREA COMMITTEE 1

Monday, October 15, 2007

HEADED ITEM NO. (2)

Report on housing construction programme

REPLY:

COMPLETIONS 2004

Cushlawn Phase 1 28

Tymon Park2

Bolbrook 11

Kilcarrig Phase 28

Russell Square 5

MarlfieldPart V26

TOTAL80

COMPLETIONS 2005

Marlfield Part V 1

Russell Square 110

Bawnlea 7

Jobstown Village Core 11

Cushlawn Ph 2 31

Daletree Part V 8

Fettercairn Village 22

TOTAL 190

COMPLETIONS 2006

Fettercairn Village 19

Deerpark Joint Venture 119

Fortunestown B Phase 2 38

Fortuenstown B Phase 4 120

Daletree Part V 24

TOTAL 320

COMPLETIONS 2007

Fortunestown B Phase 2 38

Daletree 3

Heathersett 15

Brookfield 16

Castlepark 1

TOTAL 63

SCHEMES IN PROGRESS ANTICIPATED COMPLETION DATE

Fortunestown B Phase 1 110 4th Quarter

Avonbeg Phase 3 47 4th Quarter 2007 in Phases

Heathersett part V 25 3rd & 4th Quarter 2007 in Phases

Deerpark Part V 36 4th Quarter In Phases

Castlepark 9 October 2007

Cushlawn Phase 3 22 in Phases from Deceember 2007

Greenhills Road Part V 9 December 2007

Kilcarrig Phase 3 80 4th Quarter 2008

Kiltalown Green 27 3rd Quarter 2008

Ard Mor Part V 2nd Quarter 2008

TOTAL 366

TENDER ASSESSMENT Comments

Avonbeg Phase 4 7 Anticipated start date 1st Quarter 2008

TENDER Comments

Rossfield Old Shop Site 9 Target Tender 4th Quarter 2007

Fettercairn Phase 2 33 Targer Tender 4th Quarter 2007

Fortunestown Phase 3 & 5 160 Tender advertised August 2007

Castletymon 32 Tender advertised 10th September 2007

TOTAL 234

PART 8 APPROVED

Knockmore 96 Budget Cost Approval by DOEHLG. Details being finalised with Barnardos

Stocking Lane 103 Part 8 approved June Council Meeting

Deerpark 8 Part 8 approved at July Council Meeting

TOTAL 207

CONCEPT/ DESIGN STAGE Comments

Suncroft 10 - possible affordable option. Concept to ACM 14/12/2006

Swiftbrook 11 Concept to ACM 8/12/2004

TOTAL 21

Other potential sites are also being examined