COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE 1
Monday, October 15, 2007
HEADED ITEM NO. (2)
Report on housing construction programme
REPLY:
COMPLETIONS 2004
Cushlawn Phase 1 28
Tymon Park2
Bolbrook 11
Kilcarrig Phase 28
Russell Square 5
MarlfieldPart V26
TOTAL80
COMPLETIONS 2005
Marlfield Part V 1
Russell Square 110
Bawnlea 7
Jobstown Village Core 11
Cushlawn Ph 2 31
Daletree Part V 8
Fettercairn Village 22
TOTAL 190
COMPLETIONS 2006
Fettercairn Village 19
Deerpark Joint Venture 119
Fortunestown B Phase 2 38
Fortuenstown B Phase 4 120
Daletree Part V 24
TOTAL 320
COMPLETIONS 2007
Fortunestown B Phase 2 38
Daletree 3
Heathersett 15
Brookfield 16
Castlepark 1
TOTAL 63
SCHEMES IN PROGRESS ANTICIPATED COMPLETION DATE
Fortunestown B Phase 1 110 4th Quarter
Avonbeg Phase 3 47 4th Quarter 2007 in Phases
Heathersett part V 25 3rd & 4th Quarter 2007 in Phases
Deerpark Part V 36 4th Quarter In Phases
Castlepark 9 October 2007
Cushlawn Phase 3 22 in Phases from Deceember 2007
Greenhills Road Part V 9 December 2007
Kilcarrig Phase 3 80 4th Quarter 2008
Kiltalown Green 27 3rd Quarter 2008
Ard Mor Part V 2nd Quarter 2008
TOTAL 366
TENDER ASSESSMENT Comments
Avonbeg Phase 4 7 Anticipated start date 1st Quarter 2008
TENDER Comments
Rossfield Old Shop Site 9 Target Tender 4th Quarter 2007
Fettercairn Phase 2 33 Targer Tender 4th Quarter 2007
Fortunestown Phase 3 & 5 160 Tender advertised August 2007
Castletymon 32 Tender advertised 10th September 2007
TOTAL 234
PART 8 APPROVED
Knockmore 96 Budget Cost Approval by DOEHLG. Details being finalised with Barnardos
Stocking Lane 103 Part 8 approved June Council Meeting
Deerpark 8 Part 8 approved at July Council Meeting
TOTAL 207
CONCEPT/ DESIGN STAGE Comments
Suncroft 10 - possible affordable option. Concept to ACM 14/12/2006
Swiftbrook 11 Concept to ACM 8/12/2004
TOTAL 21
Other potential sites are also being examined