Report on housing construction programme

REPLY:

COMPLETIONS 2004

Cushlawn Phase 1 28

Tymon Park 2

Bolbrook11

Kilcarrig Ph 2 8

Russell Square5

Marlfield Part V26

Total 80

COMPLETIONS 2005

Marlfield Part V 1

Russell Square 110

Bawnlea 7

Jobstown Village Core 11

Cushlawn Ph 231

Daletree Part V 8

Fettercairn Village 22

Total 190

COMPLETIONS 2006

Fettercairn Village 19

Deerpark joint venture 119

Fortunestown B Phase 2 38

Fortunestown B Ph 4 120

Daletree Part V 24

Total320

COMPLETIONS 2007

Fortunestown B Ph 2 28

Daletree3

Heathersett15

Brookfield 16

TOTAL 62

Schemes in Progress Anticipated Completion Date

Fortunestown B 1104th Quarter 2007

Avonbeg Phase 3 47 4th Quarter 2007 in phases

Heathersett Part V253rd & 4th Quarter In phases

Deerpark Part V 36 3rd Quarter 2007

Castlepark9October2007

Cushlawn Phase 3 22 December 2007

Greenhills Road Part V 9December 2007

Kilcarrig Phase 3 80 4th Quarter 2008

Kiltalown Green27 3rd Quarter 2008

Ard mor Part V 2 2nd Quarter 2008

TOTAL 367

TENDER ASSESSMENT Comments

Avonbeg Phase 4 7Anticipated Start Date 3rd Quarter 2007

TENDERS Comments

Rossfield Old Shop Site 9 Target Tender Date3rd Quarter 2007

Fettercairn Phase 2 33Target Tender Date3rd Quarter 2007

Fortunestown B 3& 5 160Tender Advertised August 2007

Castletymon 32Tender advertised 10th September 2007

TOTAL 234

PART 8 Approved

Knockmore 96 Budget Cost approved by DoEHLG. Details being finalised withBarnardos

Stocking Lane 103Part 8 approved at June Council meeting

Deerpark 8Part 8 approved at July Council Meeting

TOTAL207

CONCEPT/DESIGN STAGE Comments

Suncroft 10Possible Afordable Option. Concept to ACM 14/12/2006

Swiftbrook 11 Concept to ACM 8/12/2004

TOTAL 21

Other potential sites are also being examined