Report on housing construction programme

REPLY:

The up-to-date position of the Housing Construction Programme for the Terenure - Rathfarnham Area is set out in the detail below:-

COMPLETIONS 2004

Whitechurch Phase 3

Number of Units : 9

COMPLETIONS 2005

Whitechurch Phase3

Number of Units : 10

SCHEMES ON SITE ANTICIPATED COMPLETION DATE

Whitechurch Phase 4

Anticipated Completion Date : 29 units In Phases from Nov2007+ Community Facility

Whitechurch Phase 5

Anticipated Completion Date : 7 units Jan-08

TENDERS APPROVED

N/A

PART 8 PROCESS

Taylors Lane 9

Anticipated Start of Part 8 Process : Submissions & Observations by the 5th of September 2007. Part 8 Report to be submitted to October ACM