QUESTION NO. 7
QUESTION: Councillor G. O'Connell
To ask the Manager what is the revised timescale for completing the (a) work at the M50/N4 interchange, (b) work on the the M50/N7 interchange and (c) completion of the current phase of the M50 upgrade? And to make a statement on progress to date including reasons for delaying the completion date?
REPLY:
The M50 Upgrade Design & Build Contract 1 was commenced in March 2006 with a construction period of 24 months. The Contractor's Programme is as follows;
Substantial Completion of Ballymount Interchange September 2007
Substantial Completion of N4/M50 Interchange December 2007
Substantial Completion of Mainline Ballymount to N4 Interchange December 2007
Substantial Completion of N7/M50 Interchange October 2008*
*Completion of the N7 Interchange is delayed as a consequence of accepting the Design & Build Contractor's "Value Engineering Offer" in respect of an "Enhanced N7 Luas Free-flow Option" in which a section of the Luas Tramway at the Red Cow will be realigned on to a segregated corridor to eliminate road traffic / tram crossings.