Report on housing construction programme
The up-to-date position of the Housing Construction Programme for the Terenure - Rathfarnham Area is set out in the detail below:-
COMPLETIONS 2004 |
NUMBER OF UNITS |
|
Whitechurch Phase 3 |
9 |
|
COMPLETIONS 2005 | ||
Whitechurch Phase 3 | 10 | |
SCHEMES ON SITE | ANTICIPATED COMPLETION DATE | |
Whitechurch Phase 4 | 29 | December 2007 + Community Facility |
Whitechurch Phase 5 | 7 | December 2007 |
TENDERS APPROVED | ANTICIPATED START DATE | |
DESIGN STAGE | ANTICIPATED START OF PART 8 PROCESS | |
Kingston / Glendoher | 9 | Mid June 2007 |