COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

MEETING OF TERENURE-RATHFARNHAM AREA COMMITTEE (2)
Tuesday 12th June 2007
HEADED ITEM No. 2
Report on housing construction programme
The up-to-date position of the Housing Construction Programme for the Terenure - Rathfarnham Area is set out in the detail below:-
| COMPLETIONS 2004 |
NUMBER OF UNITS |
|
| Whitechurch Phase 3 |
9 |
|
| COMPLETIONS 2005 | ||
| Whitechurch Phase 3 | 10 | |
| SCHEMES ON SITE | ANTICIPATED COMPLETION DATE | |
| Whitechurch Phase 4 | 29 | December 2007 + Community Facility |
| Whitechurch Phase 5 | 7 | December 2007 |
| TENDERS APPROVED | ANTICIPATED START DATE | |
| DESIGN STAGE | ANTICIPATED START OF PART 8 PROCESS | |
| Kingston / Glendoher | 9 | Mid June 2007 |