The up-to-date position of the Housing Construction Programme is set out in detail below:-

 COMPLETIONS 2004    SCHEME NAME  NUMBER OF UNITS
     Cushlawn Phase1  28
     Tymon Park  2
     Bolbrook  11
     Kilcarrig Phase 2  8
     Russell Square  5
     Marlfield (Part V)  26
     Total  80
       
 COMPLETIONS 2005    Marlfield (Part V)  1
     Russell Square  110
     Bawnlea  7
     Jobstown Village Core  11
     Cushlawn Phase 2  31
     Daletree (Part V)  8
     Fettercairn Village  22
     Total  190
       
 COMPLETIONS 2006    Fettercairn Village  19
     Deerpark (Joint Venture)  119
     Fortunestown B Phase 2  38
     Fortunestown B Phase 4  120
     Daletree (Part V)  24
     Total  320
       
 COMPLETIONS 2007    Fortunestown B Phase 2  28
     Total  28
       
 SCHEMES IN PROGRESS  SCHEME NAME   NUMBER OF UNITS  ANTICIPATED COMPLETION DATE
 

 Fortunestown B Phase 1

 110

 In phases during 2007

 

 Avonbeg Phase 3

 47

 Second Quarter 2007

 

 Heathersett (Part V)

 40

 In phases from Second Quarter 2007

 

 Brookfield Village

 16 + community facility

 June 2007

 

 Daletree (Part V)

 3

 Second Quarter 2007

 

 Deerpark (Part V)

 36

 Second Quarter 2007

 

Castlepark 

 9

 June 2007

 

Cushlawn Phase 3

 22

 December 2007

 

Greenhills Road ( Part V)

 9

 December 2007

 

Kilcarrig Phase 3

 80

 4th Quarter 2008

 

Kiltalown Green

 27  3rd Quarter 2008
  Ard Mor (Part V)   2  2nd Quarter 2008
 Total  401  
       
       
 TENDER ASSESSMENT  SCHEME NAME  NUMBER OF UNITS  COMMENTS
   Avonbeg Phase 4  7  Tender approval awaited from DoEHLG
       
 TENDER PRODUCTION  SCHEME NAME  NUMBER OF UNITS  COMMENTS
   Rossfield (Old Shop Site)  9 Target Tender date 2nd Quarter 2007 
  Fettercairn Phase 2   33 Target Tender date 2nd Quarter 2007 
  Total  42   
       
PART 8 APPROVED BY COUNCIL   SCHEME NAME  NUMBER OF UNITS  COMMENTS
  Fortunestown B Phases 3 & 5  160 Draft procurement plan for affordable scheme being prepared 
  Knockmore House  (including 15 no. units for Barnardos)  96 Budget Cost approved by DoEHLG. Barnardos to finalise funding arrangements  
  Castletymon  32  Cost Plan submitted to DoEHLG for approval on 27/02/2007
   Total   288  
CONCEPT / DESIGN STAGE   SCHEME NAME  NUMBER OF UNITS  COMMENTS
   Suncroft  10  Possible affordable option. Concept presented to ACM on 14/12/2006
   Stocking Lane  150  Concept presented to ACM in June 2006
   Swiftbrook  11  Concept presented to ACM on 8/12/2004
   Deerpark Infill  9  Concept presented to ACM on 20/11/2006
   Total  180  

 Other potential sites are also being examined