Report on Housing Construction Programme
The up-to-date position of the Housing Construction Programme is set out in detail below:-
| COMPLETIONS 2004 | SCHEME NAME | NUMBER OF UNITS | |
| Cushlawn Phase1 | 28 | ||
| Tymon Park | 2 | ||
| Bolbrook | 11 | ||
| Kilcarrig Phase 2 | 8 | ||
| Russell Square | 5 | ||
| Marlfield (Part V) | 26 | ||
| Total | 80 | ||
| COMPLETIONS 2005 | Marlfield (Part V) | 1 | |
| Russell Square | 110 | ||
| Bawnlea | 7 | ||
| Jobstown Village Core | 11 | ||
| Cushlawn Phase 2 | 31 | ||
| Daletree (Part V) | 8 | ||
| Fettercairn Village | 22 | ||
| Total | 190 | ||
| COMPLETIONS 2006 | Fettercairn Village | 19 | |
| Deerpark (Joint Venture) | 119 | ||
| Fortunestown B Phase 2 | 38 | ||
| Fortunestown B Phase 4 | 120 | ||
| Daletree (Part V) | 24 | ||
| Total | 320 | ||
| COMPLETIONS 2007 | Fortunestown B Phase 2 | 28 | |
| Total | 28 | ||
| SCHEMES IN PROGRESS | SCHEME NAME | NUMBER OF UNITS | ANTICIPATED COMPLETION DATE |
|
Fortunestown B Phase 1 |
110 |
In phases from early 2007 |
|
|
|
Avonbeg Phase 3 |
47 |
March 2007 |
|
|
Heathersett (Part V) |
40 |
In phases from First Quarter 2007 |
|
|
Brookfield Village |
16 + community facility |
June 2007 |
|
|
Daletree (Part V) |
3 |
Second Quarter 2007 |
|
|
Deerpark (Part V) |
36 |
First Quarter 2007 |
|
|
Castlepark |
9 |
June 2007 |
|
|
Cushlawn Phase 3 |
22 |
December 2007 |
|
|
Greenhills Road ( Part V) |
9 |
December 2007 |
|
|
Kilcarrig Phase 3 |
80 |
4th Quarter 2008 |
|
|
Kiltalown Green |
27 | 3rd Quarter 2008 |
| Total | 399 | ||
| TENDER ASSESSMENT | SCHEME NAME | NUMBER OF UNITS | COMMENTS |
| Avonbeg Phase 4 | 7 | Tender being assessed | |
| TENDER PRODUCTION | SCHEME NAME | NUMBER OF UNITS | COMMENTS |
| Rossfield (Old Shop Site) | 9 | Target Tender date 2nd Quarter 2007 | |
| Fettercairn Phase 2 | 33 | Target Tender date 2nd Quarter 2007 | |
| Total | 42 | ||
| PART 8 APPROVED BY COUNCIL | SCHEME NAME | NUMBER OF UNITS | COMMENTS |
| Fortunestown B Phases 3 & 5 | 160 | Draft procurement plan for affordable scheme being prepared | |
| Knocmore House (including 15 no. units for Barnardos) | 96 | Cost Plan submitted to DoEHLG 23rd November 2006 (including 6 no. units at Donomore Avenue) | |
| Castletymon | 32 | Cost Plan submitted to DoEHLG for approval on 27/02/2007 | |
| Total | 288 | ||
| CONCEPT / DESIGN STAGE | SCHEME NAME | NUMBER OF UNITS | COMMENTS |
| Suncroft | 10 | Possible affordable option. Concept presented to ACM on 14/12/2006 | |
| Stocking Lane | 150 | Concept presented to ACM in June 2006 | |
| Swiftbrook | 11 | Concept presented to ACM on 8/12/2004 | |
| Deerpark Infill | 9 | Concept presented to ACM on 20/11/2006 | |
| Total | 180 |
Other potential sites are also being examined