QUESTION 10

QUESTION: Councillor M. Corr

"To ask the Manager to provide details of forthcoming Affordable Units in the Tallaght South and Tallaght Central area - giving details of expected completion dates and the numbers of units coming on stream?

REPLY

The Councils Housing Strategy, which was prepared in accordance with Part V of the Planning and Development Act 2000, was adopted by the Council at its meeting held on 11th June 2001. This Strategy was reviewed and now forms an integral part of the County development Plan 2004-2010, which was adopted by the Council on 10th November 2004.

The Strategy requires 15% of all residential developments to be reserved for Social/Affordable purposes. The Council has been successful in the delivery of affordable housing under the following initiatives:

(a)  Part V of the Planning & Development Act 2000 (as amended)

(b)  Joint Venture Schemes

(c)  Integrated Area Plans

 To date 478 affordable units have been procured throughout the County.  Of these 322 have been procured and 302 have been sold on in the Tallaght Area.

The following schedule sets out (a) a schedule of social/affordable units to be procured where a Letter of Exchange has issued and/or an Agreement has beeen reached, (b)schedule of developments where a Commencement Notice has been served and negotiations are ongoing with the developer.

 (a) Schedule of Affordable Units to be procured where a Letter of Exchange has issued and/or an Agreement has been reached.

  

Location

No. of Units Target Completion Date for units
Tallaght Cross, Belgard Square North  66  2007
Deerpark, Kiltipper Road  18  April 2007
 Hunters Lane, Hunterswood  9 April 2007
 Verschoyle Park, Saggart  2 April 2007
 Suncroft  2  2007
 Carrigmore/Carraig Court, Fortunestown  40  2007
Blackthorn, Rathcoole   16  2007
Belfry, Block E   8  2007
 Total 161  

 (b) Schedule of developments where a Commencment Notice has been served and negotiations are ongoing with the developer

 Location

Estimated Number of units for Affordable

Target Completion Date for Units*

Tallaght Leisure Centre, Old Bawn Road  3 units  Mid 2007
Former Iceland Site, Tallaght Road  32 units  Mid 2007
Tallaght Retail Unit  16 units  2007
Citywest Shopping Centre  40 units  September 2007
Marlfield  28 units  2007
Tallaght Cross, Belgard Square North  76 units (social/afford)  Mid 2007
Boherboy Road/Watercross, Saggart  34 units (social/afford)  2007
The Bungalow, Main Street, Rathcoole  21 units Mid 2007
Swiftbrook, Saggart  48 units (social/afford)  2007
Killinarden Shopping Centre  4 units  2007
Former Cats and Dogs Home, Stocking Lane  103 units (social/afford) 2007
 Total  405 units  

* Please note that the foregoing schedule provides an estimate only of units to be procured pursuant to Part V as no formal agreements have yet been reached with the developers.  Please also note that date of procurement may change due to external factors, outside the control of the Council, e.g. registration of title issue, climatic conditions etc.

 In addition to the foregoing, there is potential to procure a further 206(approx.) social/affordable units in the Tallaght Area on foot of Planning Permissions granted.