MEETING OF TERENURE-RATHFARNHAM AREA COMMITTEE 2

Tuesday, March 13, 2007

HEADED ITEM 2 (B)

Report on housing construction programme.

The up-to-date position of the construction programme for is set out in the detail below: -  

COMPLETIONS 2004

Scheme Name 

No. Of Units 

Whitechurch Phase 3 

Sub Total 

9

COMPLETIONS 2005

Scheme 

No. Of Units 

Whitechurch Phase 3 

10 

Sub Total 

10 

ON SITE:-

Scheme Name 

No. of Units 

Anticipated Completion 

Whitechurch Phase 4 (SH242)

29 

+ Community facility. December 2007 

Sub Total

29 

29 & Community facility 

TENDERS APPROVED

Scheme 

No of Units 

Whitechurch Phase 5

Negotiated Tender Report approved by The Department of the Environment Heritage and Local Government. Work due to commence shortly

Sub Total 

CONCEPT / DESIGN STAGE

Scheme Name 

No. of Units 

Kingston / Glendoher 

Palmer Park / Pearse Brothers Park 

9

Report to March ACM for further consideration. Target date for commencement of Part 8 process first quarter 2007

Other potential sites are also being examined.