COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE 1
Monday, February 19, 2007
HEADED ITEM H-I-5
Report on Implementation of Traveller Accommodation Programme 2005 – 2008,
The assessment of Traveller accommodation needs conducted in association with the process leading to the adoption of the Traveller Accommodation Programme 2005 - 2008 indicated that there is a need to provide 215 units of Traveller-specific accommodation throughout the County during the course of the programme. This accommodation is to cater for both immediate requirements and future family formations.
At the end of 2006, half-way through the currently Traveller Accommodation Programme, 51 units of Traveller-specific accommodation have been occupied by families throughout the county, eight are awaiting occupation and 15 units are currently under construction in the county.
The allocation of housing to families at Hazel Hill and Fortunestown at the end of 2006 resulted in the closure of St. Maelruan’s temporary facility.
The following is the current position on developments at various stages of delivery throughout the county:
Scheme |
Type and No. of Units |
Status |
Comments |
|
10 Group Houses |
Completed & Occupied |
Residents moved into houses in August 2005. |
|
10 bay RCP |
Completed & Occupied |
Residents moved into houses in August 2005. |
St. Aidan’s Close
|
5 Group Houses |
Completed & Occupied |
Families moved in to houses on 3rd May 2006. |
Hazel Hill, Killinardin |
Group Houses – 5 R.C.P. – 5 Bays |
Completed & Occupied |
Residents moved into scheme in December 2006. |
Fortunestown |
10 Group Houses – |
Completed & Occupied |
Residents moved into scheme in Dec. 2006. |
Lock Road Emergency Facility |
6 bay RCP |
Completed & Occupied |
Occupied by families since May 2006. |
Total No. Occupied 51 |
Scheme |
Type and No. of Units |
Status |
Comments |
Hayden’s Lane Place |
8 GH |
Substantially completed. |
To be occupied when road widening works have progressed to an appropriate stage. |
Lynch’s Lane |
10 bay RCP & 10 GH |
Contract signed |
Construction to begin early 2007. |
Kishogue |
10-bay RCP & 10 GH |
Phase 1 - 15 units Phase 2 – 5 units |
1 Under construction 2 Contract approvals from DoEH&LG received 31/1/07. |
|
7 GH |
Tender |
Tender approval from DoEH&LG received on 25/01/2007 |
Stocking Lane |
10-bay RCP |
Tender |
Tender recommendation being finalised. |
Fonthill |
3-bay RCP & 3 GH |
Part 8 approval |
Awaiting agreement on cost of units to be provided under Part V. |
Coldcut |
8 GH |
Part 8 approval |
Construction to begin in 2007. |
|
10 GH |
Part 8 |
29th January was closing date for submissions on the proposed scheme. |
Rathcoole |
10 GH |
Pre-part 8 |
Design for revised Part 8 process for group housing to be prepared. |
|
5/6 GH |
Pre-part 8 consultation. |
Pre-part 8 meeting with site residents held in August 2006.. |
Oldcastle
Adamstown - 3 schemes units Status, 10 units each, three sites have been identified in the Strategic Development Zone.
The remaining developments, listed below, are at site identification stage:
Blackchurch - 10 units;
Brittas – 10 units;
Bustyhill - 8 units.