COMHAIRLE CHONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TERENURE-RATHFARNHAM AREA COMMITTEE 1
Tuesday, February 06, 2007
QUESTION No: 9
QUESTION: Councillor S. Laing
"To ask the Manager if he could state when the proposed link road between Limekiln Road and Greenhills Road will be constructed and if he could set out the likely time frame involved and if he will make a statement on the matter?
REPLY
The Limekiln Link Road will be constructed in conjunction with the Greenhills Road Reconfiguration. At present work is progressing on the detailed design and CPO. Construction works are anticipated to commence in late 2007 / early 2008 and the overall scheme will be due for completion by mid 2009.